The following lists represent those locally administered projects “committed” to advertise within the respective calendar year. The initial list represents the commitment “baseline” and is developed through district coordination with their respective localities.  

Commitments achieved (actual advertisements) are reported to the deputy chief engineer twice each month and are included in the “tracking” list. The tracking list is updated quarterly to include actual advertisement dates with project counts and dollar values. 

  •  2020
    • Stateside for Calendar Year 2019, the local program commitment baseline was to advertise 169 projects valued at $387 million.
    • Commitments baseline
  • 2019
    • Stateside for Calendar Year 2019, the local program commitment baseline is to advertise 169 projects valued at $387 million.
    • Calendar Year 2019 – 220 projects valued at $466 million
    • Commitments baseline
    • Commitments tracking

Prior Year Locally Administered Projects Construction Advertisements (end of year results):

  • Calendar Year 2018 – 188 projects valued at $206 million
  • Calendar Year 2017 - 229 projects valued at $327 million
  • Calendar Year 2016 - 147 projects valued at $326 million
  • Calendar Year 2015 – 168 projects valued at $287 million
  • Calendar Year 2014 – 191 projects valued at $249 million
  • Calendar Year 2013 – 186 projects valued at $284 million
  • Calendar Year 2012 – 184 projects valued at $560 million (includes Chesapeake’s Dominion Boulevard, valued at $320 million)
  • Calendar Year 2011 – 127 projects valued at $226 million
  • Calendar Year 2010 – 78 projects valued at $180 million

 