E22-PSPPROP VIRGINIA DEPARTMENT OF TRANSPORTATION PAGE: 2 CONTRACT ID : CM908PMA39672 STATE PROJ NUM: PM-9A-08 FEDERAL PROJ NUM:NONE ORDER NO. 902 DATE 01/08/08 SCHEDULE OF ITEMS REVISED CONTRACTOR :____________________________________________________________________ -------------------------------------------------------------------------------- MC | LINE| ITEM | ITEM | APP QTY.| UNIT PRICE | BID AMOUNT |------------| DESCRIPTION |---------|--------------|-------------- |SPEC NUMBER | | UNITS | DOLLARS|CTS | DOLLARS|CTS -------------------------------------------------------------------------------- | COMMON ITEMS -------------------------------------------------------------------------------- |0010 | 16242|AGGR. BASE MATL. TY. I | 3924| | |------------|OR II NO. 21A OR 21B |---------| | |ATTD | | TON | | | | -------------------------------------------------------------------------------- A |0020 | 16330|ASPHALT CONCRETE | 1064| | |------------|TY. SM-9.0A |---------| | |315 | | TON | | | | -------------------------------------------------------------------------------- A |0030 | 16335|ASPHALT CONCRETE | 19694| | |------------|TY. SM-9.5A |---------| | |315 | | TON | | | | -------------------------------------------------------------------------------- A |0040 | 16340|ASPHALT CONCRETE | 30254| | |------------|TY. SM-9.5D |---------| | |315 | | TON | | | | -------------------------------------------------------------------------------- A |0050 | 16365|ASPHALT CONCRETE | 1392| | |------------|TY. IM-19.0A |---------| | |315 | | TON | | | | -------------------------------------------------------------------------------- A |0060 | 16375|ASPHALT CONCRETE | 310| | |------------|TY. BM-25.0 |---------| | |315 | | TON | | | | -------------------------------------------------------------------------------- A |0070 | 16376|ASPH. CONC. TY. | 2438| | |------------|BM-25.0T (TRENCHING) |---------| | |315 | | TON | | | | -------------------------------------------------------------------------------- |0080 | 16388|FLEXIBLE PAVEMENT | 1407214| | |------------|PLANING (MAINTENANCE) |---------| | |ATTD | | SY | | | | -------------------------------------------------------------------------------- |0090 | 51615|14/1 ENCLOSED COND. | 33432| | |------------|CABLE |---------| | |700 | | LF | | | | -------------------------------------------------------------------------------- |0100 | 51912|SAW CUT 3/8" | 11088| | |------------| |---------| | |703 | | LF | | | | -------------------------------------------------------------------------------- |0110 | 51913|SAWCUT 5/8" | 1260| | |------------| |---------| | |703 | | LF | | | | -------------------------------------------------------------------------------- A = PRICE ADJUSTMENT ITEM M = MAJOR ITEM S = SPECIALTY ITEM F = FUEL ADJUSTMENT ITEM P = PLAN QUANTITY E22-PSPPROP VIRGINIA DEPARTMENT OF TRANSPORTATION PAGE: 3 CONTRACT ID : CM908PMA39672 STATE PROJ NUM: PM-9A-08 FEDERAL PROJ NUM:NONE ORDER NO. 902 DATE 01/08/08 SCHEDULE OF ITEMS REVISED CONTRACTOR :____________________________________________________________________ -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- |0120 | 54032|TYPE B CLASS I PAVE. | 407391| | |------------|LINE MARKING 4" |---------| | |704 | | LF | | | | -------------------------------------------------------------------------------- |0130 | 54034|TYPE B CLASS I PAVE. | 6532| | |------------|LINE MARKING 6" |---------| | |704 | | LF | | | | -------------------------------------------------------------------------------- |0140 | 54037|TYPE B CLASS I PAVE. | 5260| | |------------|LINE MARKING 8" |---------| | |704 | | LF | | | | -------------------------------------------------------------------------------- |0150 | 54040|TYPE B CLASS I PAVE. | 600| | |------------|LINE MARKING 12" |---------| | |704 | | LF | | | | -------------------------------------------------------------------------------- |0160 | 54042|TYPE B CLASS I PAVE. | 4265| | |------------|LINE MARKING 24" |---------| | |704 | | LF | | | | -------------------------------------------------------------------------------- |0170 | 54075|TYPE B CLASS VI PAVE. | 66212| | |------------|LINE MARKING 4" |---------| | |ATTD704 | | LF | | | | -------------------------------------------------------------------------------- |0180 | 54077|TYPE B CLASS VI PAVE. | 1550| | |------------|LINE MARKING 8" |---------| | |ATTD704 | | LF | | | | -------------------------------------------------------------------------------- |0190 | 54101|PAVEMENT MARKING | 18| | |------------|HANDICAPPED |---------| | |ATTD | |EA | | | | -------------------------------------------------------------------------------- |0200 | 54101|PAVEMENT MARKING | 1| | |------------|SPEED HUMP |---------| | |ATTD | |EA | | | | -------------------------------------------------------------------------------- |0210 | 54217|SNOW PLOW. RAISED | 1659| | |------------|PAVE. MARKER ASPH.CONC |---------| | |704 | | EA | | | | -------------------------------------------------------------------------------- |0220 | 54254|PAVEMENT MESSAGE MARK. | 26| | |------------|BICYCLE LANE SYMBOL |---------| | |704 | | EA | | | | -------------------------------------------------------------------------------- |0230 | 54300|PAVEMENT MESSAGE MARK. | 128| | |------------|ELONGATED ARROW SINGLE |---------| | |704 | | EA | | | | -------------------------------------------------------------------------------- A = PRICE ADJUSTMENT ITEM M = MAJOR ITEM S = SPECIALTY ITEM F = FUEL ADJUSTMENT ITEM P = PLAN QUANTITY E22-PSPPROP VIRGINIA DEPARTMENT OF TRANSPORTATION PAGE: 4 CONTRACT ID : CM908PMA39672 STATE PROJ NUM: PM-9A-08 FEDERAL PROJ NUM:NONE ORDER NO. 902 DATE 01/08/08 SCHEDULE OF ITEMS REVISED CONTRACTOR :____________________________________________________________________ -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- |0240 | 54400|PAVEMENT MESSAGE MARK. | 3| | |------------|"ONLY" |---------| | |704 | | EA | | | | -------------------------------------------------------------------------------- |0250 | 54401|PAVE. MESSAGE MARK. | 6| | |------------|SCHOOL ZONE |---------| | |704 | | EA | | | | -------------------------------------------------------------------------------- |0260 | 54404|PAVE. MESSAGE MARK. | 2| | |------------|R/R CROSSING |---------| | |704 | | EA | | | | -------------------------------------------------------------------------------- |0270 | 56022|1" METAL CONDUIT | 510| | |------------| |---------| | |700 | | LF | | | | -------------------------------------------------------------------------------- | TOTAL ITEMS IN SECTION 0001 | | | -------------------------------------------------------------------------------- | TOTAL BID | | | -------------------------------------------------------------------------------- | | | | | | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- | | | | | | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- | | | | | | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- | | | | | | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- | | | | | | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- | | | | | | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- A = PRICE ADJUSTMENT ITEM M = MAJOR ITEM S = SPECIALTY ITEM F = FUEL ADJUSTMENT ITEM P = PLAN QUANTITY E22-PSPPROP VIRGINIA DEPARTMENT OF TRANSPORTATION PAGE: 2 CONTRACT ID : CM908PMB39672 STATE PROJ NUM: PM-9B-08 FEDERAL PROJ NUM:NONE ORDER NO. 903 DATE 01/08/08 SCHEDULE OF ITEMS REVISED CONTRACTOR :____________________________________________________________________ -------------------------------------------------------------------------------- MC | LINE| ITEM | ITEM | APP QTY.| UNIT PRICE | BID AMOUNT |------------| DESCRIPTION |---------|--------------|-------------- |SPEC NUMBER | | UNITS | DOLLARS|CTS | DOLLARS|CTS -------------------------------------------------------------------------------- | COMMON ITEMS -------------------------------------------------------------------------------- A |0010 | 16335|ASPHALT CONCRETE | 16655| | |------------|TY. SM-9.5A |---------| | |315 | | TON | | | | -------------------------------------------------------------------------------- A |0020 | 16340|ASPHALT CONCRETE | 32325| | |------------|TY. SM-9.5D |---------| | |315 | | TON | | | | -------------------------------------------------------------------------------- A |0030 | 16375|ASPHALT CONCRETE | 24905| | |------------|TY. BM-25.0 |---------| | |315 | | TON | | | | -------------------------------------------------------------------------------- A |0040 | 16376|ASPH. CONC. TY. | 243| | |------------|BM-25.0T (TRENCHING) |---------| | |315 | | TON | | | | -------------------------------------------------------------------------------- |0050 | 16388|FLEXIBLE PAVEMENT | 2167596| | |------------|PLANING (MAINTENANCE) |---------| | |ATTD | | SY | | | | -------------------------------------------------------------------------------- |0060 | 16389|FLEXIBLE PAVEMENT EDGE | 24078| | |------------|PLANING (MAINTENANCE) |---------| | |ATTD | | SY | | | | -------------------------------------------------------------------------------- |0070 | 51615|14/1 ENCLOSED COND. | 87560| | |------------|CABLE |---------| | |700 | | LF | | | | -------------------------------------------------------------------------------- |0080 | 51912|SAW CUT 3/8" | 29040| | |------------| |---------| | |703 | | LF | | | | -------------------------------------------------------------------------------- |0090 | 51913|SAWCUT 5/8" | 3300| | |------------| |---------| | |703 | | LF | | | | -------------------------------------------------------------------------------- |0100 | 54032|TYPE B CLASS I PAVE. | 176790| | |------------|LINE MARKING 4" |---------| | |704 | | LF | | | | -------------------------------------------------------------------------------- |0110 | 54034|TYPE B CLASS I PAVE. | 13350| | |------------|LINE MARKING 6" |---------| | |704 | | LF | | | | -------------------------------------------------------------------------------- A = PRICE ADJUSTMENT ITEM M = MAJOR ITEM S = SPECIALTY ITEM F = FUEL ADJUSTMENT ITEM P = PLAN QUANTITY E22-PSPPROP VIRGINIA DEPARTMENT OF TRANSPORTATION PAGE: 3 CONTRACT ID : CM908PMB39672 STATE PROJ NUM: PM-9B-08 FEDERAL PROJ NUM:NONE ORDER NO. 903 DATE 01/08/08 SCHEDULE OF ITEMS REVISED CONTRACTOR :____________________________________________________________________ -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- |0120 | 54037|TYPE B CLASS I PAVE. | 800| | |------------|LINE MARKING 8" |---------| | |704 | | LF | | | | -------------------------------------------------------------------------------- |0130 | 54042|TYPE B CLASS I PAVE. | 33657| | |------------|LINE MARKING 24" |---------| | |704 | | LF | | | | -------------------------------------------------------------------------------- |0140 | 54075|TYPE B CLASS VI PAVE. | 128787| | |------------|LINE MARKING 4" |---------| | |ATTD704 | | LF | | | | -------------------------------------------------------------------------------- |0150 | 54077|TYPE B CLASS VI PAVE. | 5710| | |------------|LINE MARKING 8" |---------| | |ATTD704 | | LF | | | | -------------------------------------------------------------------------------- |0160 | 54101|PAVEMENT MARKING | 4| | |------------|SPEED HUMP |---------| | |ATTD | |EA | | | | -------------------------------------------------------------------------------- |0170 | 54105|ERADICATION OF EXIST. | 4000| | |------------|PAVEMENT MARKING |---------| | |512 | | LF | | | | -------------------------------------------------------------------------------- |0180 | 54254|PAVEMENT MESSAGE MARK. | 24| | |------------|BICYCLE LANE SYMBOL |---------| | |704 | | EA | | | | -------------------------------------------------------------------------------- |0190 | 54300|PAVEMENT MESSAGE MARK. | 289| | |------------|ELONGATED ARROW SINGLE |---------| | |704 | | EA | | | | -------------------------------------------------------------------------------- |0200 | 54400|PAVEMENT MESSAGE MARK. | 2| | |------------|"ONLY" |---------| | |704 | | EA | | | | -------------------------------------------------------------------------------- |0210 | 54401|PAVE. MESSAGE MARK. | 3| | |------------|SCHOOL ZONE |---------| | |704 | | EA | | | | -------------------------------------------------------------------------------- |0220 | 56022|1" METAL CONDUIT | 1525| | |------------| |---------| | |700 | | LF | | | | -------------------------------------------------------------------------------- | TOTAL ITEMS IN SECTION 0001 | | | -------------------------------------------------------------------------------- | TOTAL BID | | | -------------------------------------------------------------------------------- A = PRICE ADJUSTMENT ITEM M = MAJOR ITEM S = SPECIALTY ITEM F = FUEL ADJUSTMENT ITEM P = PLAN QUANTITY E22-PSPPROP VIRGINIA DEPARTMENT OF TRANSPORTATION PAGE: 2 CONTRACT ID : CM908PMC39672 STATE PROJ NUM: PM-9C-08 FEDERAL PROJ NUM:NONE ORDER NO. 904 DATE 01/08/08 SCHEDULE OF ITEMS REVISED CONTRACTOR :____________________________________________________________________ -------------------------------------------------------------------------------- MC | LINE| ITEM | ITEM | APP QTY.| UNIT PRICE | BID AMOUNT |------------| DESCRIPTION |---------|--------------|-------------- |SPEC NUMBER | | UNITS | DOLLARS|CTS | DOLLARS|CTS -------------------------------------------------------------------------------- | COMMON ITEMS -------------------------------------------------------------------------------- |0010 | 16242|AGGR. BASE MATL. TY. I | 1143| | |------------|OR II NO. 21A OR 21B |---------| | |ATTD | | TON | | | | -------------------------------------------------------------------------------- A |0020 | 16330|ASPHALT CONCRETE | 2912| | |------------|TY. SM-9.0A |---------| | |315 | | TON | | | | -------------------------------------------------------------------------------- A |0030 | 16335|ASPHALT CONCRETE | 706| | |------------|TY. SM-9.5A |---------| | |315 | | TON | | | | -------------------------------------------------------------------------------- A |0040 | 16340|ASPHALT CONCRETE | 60593| | |------------|TY. SM-9.5D |---------| | |315 | | TON | | | | -------------------------------------------------------------------------------- A |0050 | 16376|ASPH. CONC. TY. | 348| | |------------|BM-25.0T (TRENCHING) |---------| | |315 | | TON | | | | -------------------------------------------------------------------------------- |0060 | 16388|FLEXIBLE PAVEMENT | 1979248| | |------------|PLANING (MAINTENANCE) |---------| | |ATTD | | SY | | | | -------------------------------------------------------------------------------- |0070 | 51615|14/1 ENCLOSED COND. | 68854| | |------------|CABLE |---------| | |700 | | LF | | | | -------------------------------------------------------------------------------- |0080 | 51912|SAW CUT 3/8" | 22836| | |------------| |---------| | |703 | | LF | | | | -------------------------------------------------------------------------------- |0090 | 51913|SAWCUT 5/8" | 2595| | |------------| |---------| | |703 | | LF | | | | -------------------------------------------------------------------------------- |0100 | 54032|TYPE B CLASS I PAVE. | 108461| | |------------|LINE MARKING 4" |---------| | |704 | | LF | | | | -------------------------------------------------------------------------------- |0110 | 54034|TYPE B CLASS I PAVE. | 10680| | |------------|LINE MARKING 6" |---------| | |704 | | LF | | | | -------------------------------------------------------------------------------- A = PRICE ADJUSTMENT ITEM M = MAJOR ITEM S = SPECIALTY ITEM F = FUEL ADJUSTMENT ITEM P = PLAN QUANTITY E22-PSPPROP VIRGINIA DEPARTMENT OF TRANSPORTATION PAGE: 3 CONTRACT ID : CM908PMC39672 STATE PROJ NUM: PM-9C-08 FEDERAL PROJ NUM:NONE ORDER NO. 904 DATE 01/08/08 SCHEDULE OF ITEMS REVISED CONTRACTOR :____________________________________________________________________ -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- |0120 | 54037|TYPE B CLASS I PAVE. | 865| | |------------|LINE MARKING 8" |---------| | |704 | | LF | | | | -------------------------------------------------------------------------------- |0130 | 54040|TYPE B CLASS I PAVE. | 680| | |------------|LINE MARKING 12" |---------| | |704 | | LF | | | | -------------------------------------------------------------------------------- |0140 | 54042|TYPE B CLASS I PAVE. | 13477| | |------------|LINE MARKING 24" |---------| | |704 | | LF | | | | -------------------------------------------------------------------------------- |0150 | 54075|TYPE B CLASS VI PAVE. | 239289| | |------------|LINE MARKING 4" |---------| | |ATTD704 | | LF | | | | -------------------------------------------------------------------------------- |0160 | 54077|TYPE B CLASS VI PAVE. | 10928| | |------------|LINE MARKING 8" |---------| | |ATTD704 | | LF | | | | -------------------------------------------------------------------------------- |0170 | 54101|PAVEMENT MARKING | 1| | |------------|STOP AHEAD |---------| | |ATTD | |EA | | | | -------------------------------------------------------------------------------- |0180 | 54300|PAVEMENT MESSAGE MARK. | 187| | |------------|ELONGATED ARROW SINGLE |---------| | |704 | | EA | | | | -------------------------------------------------------------------------------- |0190 | 54400|PAVEMENT MESSAGE MARK. | 8| | |------------|"ONLY" |---------| | |704 | | EA | | | | -------------------------------------------------------------------------------- |0200 | 54401|PAVE. MESSAGE MARK. | 20| | |------------|SCHOOL ZONE |---------| | |704 | | EA | | | | -------------------------------------------------------------------------------- |0210 | 56022|1" METAL CONDUIT | 1250| | |------------| |---------| | |700 | | LF | | | | -------------------------------------------------------------------------------- | TOTAL ITEMS IN SECTION 0001 | | | -------------------------------------------------------------------------------- | TOTAL BID | | | -------------------------------------------------------------------------------- A = PRICE ADJUSTMENT ITEM M = MAJOR ITEM S = SPECIALTY ITEM F = FUEL ADJUSTMENT ITEM P = PLAN QUANTITY E22-PSPPROP VIRGINIA DEPARTMENT OF TRANSPORTATION PAGE: 2 CONTRACT ID : CM908PMD39672 STATE PROJ NUM: PM-9D-08 FEDERAL PROJ NUM:NONE ORDER NO. 907 DATE 01/08/08 SCHEDULE OF ITEMS REVISED CONTRACTOR :____________________________________________________________________ -------------------------------------------------------------------------------- MC | LINE| ITEM | ITEM | APP QTY.| UNIT PRICE | BID AMOUNT |------------| DESCRIPTION |---------|--------------|-------------- |SPEC NUMBER | | UNITS | DOLLARS|CTS | DOLLARS|CTS -------------------------------------------------------------------------------- | COMMON ITEMS -------------------------------------------------------------------------------- |0010 | 00120|REGULAR EXCAVATION | 59137| | |------------| |---------| | |303 | | CY | | | | -------------------------------------------------------------------------------- |0020 | 16242|AGGR. BASE MATL. TY. I | 8000| | |------------|OR II NO. 21A OR 21B |---------| | |ATTD | | TON | | | | -------------------------------------------------------------------------------- A |0030 | 16340|ASPHALT CONCRETE | 7533| | |------------|TY. SM-9.5D |---------| | |315 | | TON | | | | -------------------------------------------------------------------------------- A |0040 | 16365|ASPHALT CONCRETE | 9242| | |------------|TY. IM-19.0A |---------| | |315 | | TON | | | | -------------------------------------------------------------------------------- A |0050 | 16375|ASPHALT CONCRETE | 23312| | |------------|TY. BM-25.0 |---------| | |315 | | TON | | | | -------------------------------------------------------------------------------- |0060 | 16388|FLEXIBLE PAVEMENT | 1346050| | |------------|PLANING (MAINTENANCE) |---------| | |ATTD | | SY | | | | -------------------------------------------------------------------------------- |0070 | 51615|14/1 ENCLOSED COND. | 1990| | |------------|CABLE |---------| | |700 | | LF | | | | -------------------------------------------------------------------------------- |0080 | 51912|SAW CUT 3/8" | 660| | |------------| |---------| | |703 | | LF | | | | -------------------------------------------------------------------------------- |0090 | 51913|SAWCUT 5/8" | 75| | |------------| |---------| | |703 | | LF | | | | -------------------------------------------------------------------------------- |0100 | 54020|TYPE A PAVEMENT LINE | 20000| | |------------|MARKING 4" |---------| | |704 | | LF | | | | -------------------------------------------------------------------------------- |0110 | 54034|TYPE B CLASS I PAVE. | 5000| | |------------|LINE MARKING 6" |---------| | |704 | | LF | | | | -------------------------------------------------------------------------------- A = PRICE ADJUSTMENT ITEM M = MAJOR ITEM S = SPECIALTY ITEM F = FUEL ADJUSTMENT ITEM P = PLAN QUANTITY E22-PSPPROP VIRGINIA DEPARTMENT OF TRANSPORTATION PAGE: 3 CONTRACT ID : CM908PMD39672 STATE PROJ NUM: PM-9D-08 FEDERAL PROJ NUM:NONE ORDER NO. 907 DATE 01/08/08 SCHEDULE OF ITEMS REVISED CONTRACTOR :____________________________________________________________________ -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- |0120 | 54042|TYPE B CLASS I PAVE. | 1020| | |------------|LINE MARKING 24" |---------| | |704 | | LF | | | | -------------------------------------------------------------------------------- |0130 | 54075|TYPE B CLASS VI PAVE. | 47042| | |------------|LINE MARKING 4" |---------| | |ATTD704 | | LF | | | | -------------------------------------------------------------------------------- |0140 | 54300|PAVEMENT MESSAGE MARK. | 21| | |------------|ELONGATED ARROW SINGLE |---------| | |704 | | EA | | | | -------------------------------------------------------------------------------- |0150 | 54401|PAVE. MESSAGE MARK. | 4| | |------------|SCHOOL ZONE |---------| | |704 | | EA | | | | -------------------------------------------------------------------------------- |0160 | 56022|1" METAL CONDUIT | 30| | |------------| |---------| | |700 | | LF | | | | -------------------------------------------------------------------------------- | TOTAL ITEMS IN SECTION 0001 | | | -------------------------------------------------------------------------------- | TOTAL BID | | | -------------------------------------------------------------------------------- | | | | | | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- | | | | | | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- | | | | | | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- | | | | | | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- | | | | | | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- A = PRICE ADJUSTMENT ITEM M = MAJOR ITEM S = SPECIALTY ITEM F = FUEL ADJUSTMENT ITEM P = PLAN QUANTITY E22-PSPPROP VIRGINIA DEPARTMENT OF TRANSPORTATION PAGE: 2 CONTRACT ID : CM108BRA39579 STATE PROJ NUM: 0642-098-6243,SR01 FEDERAL PROJ NUM:NONE ORDER NO. A27 DATE 01/08/08 SCHEDULE OF ITEMS REVISED CONTRACTOR :____________________________________________________________________ -------------------------------------------------------------------------------- MC | LINE| ITEM | ITEM | APP QTY.| UNIT PRICE | BID AMOUNT |------------| DESCRIPTION |---------|--------------|-------------- |SPEC NUMBER | | UNITS | DOLLARS|CTS | DOLLARS|CTS -------------------------------------------------------------------------------- | COMMON ITEMS -------------------------------------------------------------------------------- |0010 | 00100|MOBILIZATION | 1| | |------------| |---------| | |513 | | LS | | | | -------------------------------------------------------------------------------- |0020 | 00101|CONSTRUCTION SURVEYING | 1| | |------------| |---------| | |105 | | LS | | | | -------------------------------------------------------------------------------- |0030 | 10607|ASPHALT CONCRETE | 39| | |------------|TY. SM-12.5A |---------| | |315 | | TON | | | | -------------------------------------------------------------------------------- P |0040 | 10630|FLEXIBLE PAVEMENT | 334| | |------------|PLANING |---------| | |515 | | SY | | | | -------------------------------------------------------------------------------- |0050 | 24152|TYPE III BARRICADE 8' | 2| | |------------| |---------| | |512 | | EA | | | | -------------------------------------------------------------------------------- |0060 | 24160|CONSTRUCTION SIGNS | 300| | |------------| |---------| | |512 | | SF | | | | -------------------------------------------------------------------------------- |0070 | 24278|GROUP 2 CHANNELIZING | 2500| | |------------|DEVICES |---------| | |512 | | DAY | | | | -------------------------------------------------------------------------------- |0080 | 24282|FLAGGER SERVICE | 200| | |------------| |---------| | |512 | | HR | | | | -------------------------------------------------------------------------------- MP |0090 | 68023|RAILING,KANSAS CORRAL | 244| | |------------|32" W/OUT CURB |---------| | |410 | | LF | | | | -------------------------------------------------------------------------------- M |0100 | 68040|CONCRETE CLASS A4 | 186| | |------------| |---------| | |404 | | CY | | | | -------------------------------------------------------------------------------- P |0110 | 68090|BRIDGE DECK GROOVING | 298| | |------------| |---------| | |404 | | SY | | | | -------------------------------------------------------------------------------- A = PRICE ADJUSTMENT ITEM M = MAJOR ITEM S = SPECIALTY ITEM F = FUEL ADJUSTMENT ITEM P = PLAN QUANTITY E22-PSPPROP VIRGINIA DEPARTMENT OF TRANSPORTATION PAGE: 3 CONTRACT ID : CM108BRA39579 STATE PROJ NUM: 0642-098-6243,SR01 FEDERAL PROJ NUM:NONE ORDER NO. A27 DATE 01/08/08 SCHEDULE OF ITEMS REVISED CONTRACTOR :____________________________________________________________________ -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- PA |0120 | 68105|EPOXY COATED REINF. | 44500| | |------------|STEEL |---------| | |412 406 | | LB | | | | -------------------------------------------------------------------------------- |0130 | 68476|ENV.& WORK. PROTECTION | 1| | ------------|STR. NO. 6243 |---------| | |413 | |LS | | | | -------------------------------------------------------------------------------- |0140 | 68492|MATERIAL DISPOSAL | 1| | ------------|STR. NO. 6243, TY. B |---------| | |413 | |LS | | | | -------------------------------------------------------------------------------- |0150 | 68710|TRAFFIC BARRIER | 48| | |------------|SERVICE CONCRETE |---------| | |512 | | LF | | | | -------------------------------------------------------------------------------- |0160 | 68900|REM. PORT. OF EX. STR. | 1| | ------------|NO. 6243 |---------| | |413 | |LS | | | | -------------------------------------------------------------------------------- P |0170 | 69009|POROUS BACKFILL | 6| | |------------| |---------| | |401 | | CY | | | | -------------------------------------------------------------------------------- P |0180 | 69011|STRUCTURE EXCAVATION | 6| | |------------| |---------| | |401 | | CY | | | | -------------------------------------------------------------------------------- A |0190 | 69100|REINF. STEEL | 80| | |------------| |---------| | |412 406 | | LB | | | | -------------------------------------------------------------------------------- |0200 | 69500|CONCRETE SUBSTRUCT. | 9| | |------------|SURFACE REPAIR |---------| | |412 | | SY | | | | -------------------------------------------------------------------------------- | TOTAL ITEMS IN SECTION 0001 | | | -------------------------------------------------------------------------------- | TOTAL BID | | | -------------------------------------------------------------------------------- | | | | | | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- A = PRICE ADJUSTMENT ITEM M = MAJOR ITEM S = SPECIALTY ITEM F = FUEL ADJUSTMENT ITEM P = PLAN QUANTITY E22-PSPPROP VIRGINIA DEPARTMENT OF TRANSPORTATION PAGE: 2 CONTRACT ID : C00084946C01 STATE PROJ NUM: (NFO) BR07-056-307, C501 FEDERAL PROJ NUM:BH-BR07(220) ORDER NO. A29 DATE 01/08/08 SCHEDULE OF ITEMS REVISED CONTRACTOR :____________________________________________________________________ -------------------------------------------------------------------------------- MC | LINE| ITEM | ITEM | APP QTY.| UNIT PRICE | BID AMOUNT |------------| DESCRIPTION |---------|--------------|-------------- |SPEC NUMBER | | UNITS | DOLLARS|CTS | DOLLARS|CTS -------------------------------------------------------------------------------- | COMMON ITEMS -------------------------------------------------------------------------------- | | | | .| | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- | TOTAL ITEMS IN SECTION 0001 | | | -------------------------------------------------------------------------------- | TOTAL BID | | | -------------------------------------------------------------------------------- | | | | | | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- | | | | | | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- | | | | | | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- | | | | | | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- | | | | | | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- | | | | | | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- | | | | | | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- | | | | | | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- A = PRICE ADJUSTMENT ITEM M = MAJOR ITEM S = SPECIALTY ITEM F = FUEL ADJUSTMENT ITEM P = PLAN QUANTITY E22-PSPPROP VIRGINIA DEPARTMENT OF TRANSPORTATION PAGE: 2 CONTRACT ID : C0084945C01 STATE PROJ NUM: BR07-030-306,C501 FEDERAL PROJ NUM:BH-BR07(218) ORDER NO. A30 DATE 01/08/08 SCHEDULE OF ITEMS REVISED CONTRACTOR :____________________________________________________________________ -------------------------------------------------------------------------------- MC | LINE| ITEM | ITEM | APP QTY.| UNIT PRICE | BID AMOUNT |------------| DESCRIPTION |---------|--------------|-------------- |SPEC NUMBER | | UNITS | DOLLARS|CTS | DOLLARS|CTS -------------------------------------------------------------------------------- | COMMON ITEMS -------------------------------------------------------------------------------- |0010 | 00100|MOBILIZATION | 1| | |------------| |---------| | |513 | | LS | | | | -------------------------------------------------------------------------------- |0020 | 00120|REGULAR EXCAVATION | 270| | |------------| |---------| | |303 | | CY | | | | -------------------------------------------------------------------------------- |0030 | 10123|AGGR. BASE MATL. TY. I | 66| | |------------|NO. 21A |---------| | |308 309 | | TON | | | | -------------------------------------------------------------------------------- |0040 | 10636|ASPHALT CONCRETE | 150| | |------------|TY. SM-9.5D |---------| | |315 | | TON | | | | -------------------------------------------------------------------------------- |0050 | 10642|ASPHALT CONCRETE | 415| | |------------|TY. BM-25.0A |---------| | |315 | | TON | | | | -------------------------------------------------------------------------------- |0060 | 10700|RUMBLE STRIP, ASPHALT | 2300| | |------------| |---------| | |ATTD | | LF | | | | -------------------------------------------------------------------------------- |0070 | 10701|LIQUID ASPHALT COATING | 426| | |------------| |---------| | |ATTD | | SY | | | | -------------------------------------------------------------------------------- |0080 | 11070|SAW CUT | 2300| | |------------|ASPH. CONC. 3" |---------| | |PLAN 315 | |LF | | | | -------------------------------------------------------------------------------- |0090 | 13315|GUARDRAIL TERMINAL | 1| | |------------|GR-11 |---------| | |505 | | EA | | | | -------------------------------------------------------------------------------- |0100 | 13320|GUARDRAIL GR-2 | 870| | |------------| |---------| | |505 | | LF | | | | -------------------------------------------------------------------------------- |0110 | 13345|ALTERNATE BREAKAWAY | 1| | |------------|CABLE TERMINAL (GR-9) |---------| | |505 | | EA | | | | -------------------------------------------------------------------------------- A = PRICE ADJUSTMENT ITEM M = MAJOR ITEM S = SPECIALTY ITEM F = FUEL ADJUSTMENT ITEM P = PLAN QUANTITY E22-PSPPROP VIRGINIA DEPARTMENT OF TRANSPORTATION PAGE: 3 CONTRACT ID : C0084945C01 STATE PROJ NUM: BR07-030-306,C501 FEDERAL PROJ NUM:BH-BR07(218) ORDER NO. A30 DATE 01/08/08 SCHEDULE OF ITEMS REVISED CONTRACTOR :____________________________________________________________________ -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- |0120 | 13349|GUARDRAIL TERMINAL | 1| | |------------|SITE PREPARATION |---------| | |505 | | EA | | | | -------------------------------------------------------------------------------- |0130 | 13385|FIXED OBJECT ATTACH. | 1| | |------------|GR-FOA-3 TY. I |---------| | |505 | | EA | | | | -------------------------------------------------------------------------------- |0140 | 13386|FIXED OBJECT ATTACH. | 1| | |------------|GR-FOA-3 TY. II |---------| | |505 | | EA | | | | -------------------------------------------------------------------------------- |0150 | 13400|GUARDRAIL | 1070| | |------------|SHOULDER RESTORATION |---------| | |ATTD | |LF | | | | -------------------------------------------------------------------------------- |0160 | 24265|MAINTENANCE OF TRAFFIC | 1| | ------------|STR. 2061 |---------| | |ATTD | |LS | | | | -------------------------------------------------------------------------------- |0170 | 24279|PORTABLE CHANGEABLE | 2500| | |------------|MESSAGE SIGN |---------| | |512 | | HR | | | | -------------------------------------------------------------------------------- |0180 | 24601|REMOVE EXIST. GUARDRAIL| 590| | |------------|ON APPROACHES |---------| | |510 PLAN | |LF | | | | -------------------------------------------------------------------------------- |0190 | 27430|SILTATION CONTROL | 34| | |------------|EXCAVATION |---------| | |303 | | CY | | | | -------------------------------------------------------------------------------- |0200 | 27506|TEMP. FILTER BARRIER | 200| | |------------| |---------| | |303 | | LF | | | | -------------------------------------------------------------------------------- |0210 | 54076|TYPE B CLASS VI PAVE. | 2800| | |------------|LINE MARKING 6" |---------| | |ATTD704 | | LF | | | | -------------------------------------------------------------------------------- |0220 | 54100|PAVEMENT MARKING | 415| | |------------|TYPE B CLASS VI 6" |---------| | |ATTD |CONTRAST |LF | | | | -------------------------------------------------------------------------------- |0230 | 60490|BRIDGE DECK GROOVING | 542| | |------------| |---------| | |404 | | SY | | | | -------------------------------------------------------------------------------- A = PRICE ADJUSTMENT ITEM M = MAJOR ITEM S = SPECIALTY ITEM F = FUEL ADJUSTMENT ITEM P = PLAN QUANTITY E22-PSPPROP VIRGINIA DEPARTMENT OF TRANSPORTATION PAGE: 4 CONTRACT ID : C0084945C01 STATE PROJ NUM: BR07-030-306,C501 FEDERAL PROJ NUM:BH-BR07(218) ORDER NO. A30 DATE 01/08/08 SCHEDULE OF ITEMS REVISED CONTRACTOR :____________________________________________________________________ -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- |0240 | 62506|JOINT SEALER | 176| | |------------|PREF. ELAS. 2" (MOD) |---------| | |ATTD | |LF | | | | -------------------------------------------------------------------------------- |0250 | 68317|MILLING | 542| | |------------|TY.A MOD.(11/4"-13/4") |---------| | |ATTD | |SY | | | | -------------------------------------------------------------------------------- |0260 | 68320|TYPE B PATCHING | 187| | |------------| |---------| | |412 | | SY | | | | -------------------------------------------------------------------------------- |0270 | 68330|TYPE C PATCHING | 8| | |------------| |---------| | |412 | | SY | | | | -------------------------------------------------------------------------------- |0280 | 68572|EXPANSION JOINT | 168| | |------------|RECONSTRUCTION |---------| | |412 | | L.F. | | | | -------------------------------------------------------------------------------- |0290 | 68574|CLEAN AND RESEAL | 82| | |------------|EXPANSION JOINT |---------| | |ATTD404 | | LF | | | | -------------------------------------------------------------------------------- |0300 | 68910|SUPERSTR. WID./REPAIR | 542| | |------------|LATEX HYD.CEM.CONC. |---------| | |412 ATTD |V.EARLY STRENG |SY | | | | -------------------------------------------------------------------------------- | TOTAL ITEMS IN SECTION 0001 | | | -------------------------------------------------------------------------------- | TOTAL BID | | | -------------------------------------------------------------------------------- | | | | | | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- | | | | | | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- | | | | | | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- A = PRICE ADJUSTMENT ITEM M = MAJOR ITEM S = SPECIALTY ITEM F = FUEL ADJUSTMENT ITEM P = PLAN QUANTITY E22-PSPPROP VIRGINIA DEPARTMENT OF TRANSPORTATION PAGE: 2 CONTRACT ID : CM5080688N01 STATE PROJ NUM: (NFO)BR07-047-183,N501 FEDERAL PROJ NUM:IM-PM05(217) ORDER NO. A33 DATE 01/08/08 SCHEDULE OF ITEMS REVISED CONTRACTOR :____________________________________________________________________ -------------------------------------------------------------------------------- MC | LINE| ITEM | ITEM | APP QTY.| UNIT PRICE | BID AMOUNT |------------| DESCRIPTION |---------|--------------|-------------- |SPEC NUMBER | | UNITS | DOLLARS|CTS | DOLLARS|CTS -------------------------------------------------------------------------------- | COMMON ITEMS -------------------------------------------------------------------------------- |0010 | 00100|MOBILIZATION | 1| | |------------| |---------| | |513 | | LS | | | | -------------------------------------------------------------------------------- |0020 | 24265|MAINTENANCE OF TRAFFIC | 1| | ------------|STR. NO. 6006 |---------| | |ATTD | |LS | | | | -------------------------------------------------------------------------------- |0030 | 24265|MAINTENANCE OF TRAFFIC | 1| | ------------|STR. NO. 6007 |---------| | |ATTD | |LS | | | | -------------------------------------------------------------------------------- |0040 | 68472|RECOAT EX. STR. | 1| | ------------|(STR. NO. 6006, TY. B) |---------| | |411 | |LS | | | | -------------------------------------------------------------------------------- |0050 | 68472|RECOAT EX. STR. | 1| | ------------|(STR. NO. 6007, TY. B) |---------| | |411 | |LS | | | | -------------------------------------------------------------------------------- |0060 | 68474|ENV. PROT.& HEAL.SAFETY| 1| | ------------|(STR. NO. 6006) |---------| | |411 | |LS | | | | -------------------------------------------------------------------------------- |0070 | 68474|ENV. PROT.& HEAL.SAFETY| 1| | ------------|(STR. NO. 6007) |---------| | |411 | |LS | | | | -------------------------------------------------------------------------------- |0080 | 68490|DISPOSAL OF MATERIAL | 1| | ------------|(STR. NO. 6006, TY. B) |---------| | |411 | |LS | | | | -------------------------------------------------------------------------------- |0090 | 68490|DISPOSAL OF MATERIAL | 1| | ------------|(STR. NO. 6007, TY. B) |---------| | |411 | |LS | | | | -------------------------------------------------------------------------------- | TOTAL ITEMS IN SECTION 0001 | | | -------------------------------------------------------------------------------- | TOTAL BID | | | -------------------------------------------------------------------------------- A = PRICE ADJUSTMENT ITEM M = MAJOR ITEM S = SPECIALTY ITEM F = FUEL ADJUSTMENT ITEM P = PLAN QUANTITY E22-PSPPROP VIRGINIA DEPARTMENT OF TRANSPORTATION PAGE: 2 CONTRACT ID : CM108BRA39537 STATE PROJ NUM: 0613-084-6012,SR01 FEDERAL PROJ NUM:NONE ORDER NO. A34 DATE 01/08/08 SCHEDULE OF ITEMS REVISED CONTRACTOR :____________________________________________________________________ -------------------------------------------------------------------------------- MC | LINE| ITEM | ITEM | APP QTY.| UNIT PRICE | BID AMOUNT |------------| DESCRIPTION |---------|--------------|-------------- |SPEC NUMBER | | UNITS | DOLLARS|CTS | DOLLARS|CTS -------------------------------------------------------------------------------- | COMMON ITEMS -------------------------------------------------------------------------------- |0010 | 00100|MOBILIZATION | 1| | |------------| |---------| | |513 | | LS | | | | -------------------------------------------------------------------------------- |0020 | 00101|CONSTRUCTION SURVEYING | 1| | |------------| |---------| | |105 | | LS | | | | -------------------------------------------------------------------------------- |0030 | 00120|REGULAR EXCAVATION | 200| | |------------| |---------| | |303 | | CY | | | | -------------------------------------------------------------------------------- |0040 | 00140|BORROW EXCAVATION | 1200| | |------------| |---------| | |303 305 | | CY | | | | -------------------------------------------------------------------------------- |0050 | 00270|SELECT MATL. | 1039| | |------------|TY. I MIN. CBR-30 |---------| | |305 | | TON | | | | -------------------------------------------------------------------------------- |0060 | 01182|18" CONC. PIPE | 26| | |------------| |---------| | |302 | | LF | | | | -------------------------------------------------------------------------------- |0070 | 06181|18" END SECTION ES-1 | 2| | |------------| |---------| | |302 | | EA | | | | -------------------------------------------------------------------------------- |0080 | 10128|AGGR. BASE MATL. TY. I | 475| | |------------|NO. 21B |---------| | |308 309 | | TON | | | | -------------------------------------------------------------------------------- |0090 | 10598|ASPHALT CONCRETE | 96| | |------------|TY. SM-19.0A |---------| | |315 | |TON | | | | -------------------------------------------------------------------------------- |0100 | 13212|R/W MONUMENT RM-2 | 4| | |------------| |---------| | |503 | | EA | | | | -------------------------------------------------------------------------------- A |0110 | 13320|GUARDRAIL GR-2 | 38| | |------------| |---------| | |505 | | LF | | | | -------------------------------------------------------------------------------- A = PRICE ADJUSTMENT ITEM M = MAJOR ITEM S = SPECIALTY ITEM F = FUEL ADJUSTMENT ITEM P = PLAN QUANTITY E22-PSPPROP VIRGINIA DEPARTMENT OF TRANSPORTATION PAGE: 3 CONTRACT ID : CM108BRA39537 STATE PROJ NUM: 0613-084-6012,SR01 FEDERAL PROJ NUM:NONE ORDER NO. A34 DATE 01/08/08 SCHEDULE OF ITEMS REVISED CONTRACTOR :____________________________________________________________________ -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- A |0120 | 13331|RAD. GUARDRAIL GR-2 | 13| | |------------| |---------| | |505 | | LF | | | | -------------------------------------------------------------------------------- A |0130 | 13345|ALTERNATE BREAKAWAY | 3| | |------------|CABLE TERMINAL (GR-9) |---------| | |505 | | EA | | | | -------------------------------------------------------------------------------- A |0140 | 13383|FIXED OBJECT ATTACH. | 4| | |------------|GR-FOA-1 TY. I |---------| | |505 | | EA | | | | -------------------------------------------------------------------------------- |0150 | 24100|ALLAYING DUST | 100| | |------------| |---------| | |511 | | HR | | | | -------------------------------------------------------------------------------- |0160 | 24152|TYPE III BARRICADE 8' | 2| | |------------| |---------| | |512 | | EA | | | | -------------------------------------------------------------------------------- |0170 | 24160|CONSTRUCTION SIGNS | 288| | |------------| |---------| | |512 | | SF | | | | -------------------------------------------------------------------------------- |0180 | 24260|CR. RUN AGGR. | 500| | |------------|NO. 25 OR 26 |---------| | |512 | | TON | | | | -------------------------------------------------------------------------------- |0190 | 24278|GROUP 2 CHANNELIZING | 3960| | |------------|DEVICES |---------| | |512 | | DAY | | | | -------------------------------------------------------------------------------- |0200 | 24282|FLAGGER SERVICE | 100| | |------------| |---------| | |512 | | HR | | | | -------------------------------------------------------------------------------- |0210 | 24290|TRAFFIC BARRIER | 288| | |------------|SERVICE CONCRETE |---------| | |512 | | LF | | | | -------------------------------------------------------------------------------- P |0220 | 24430|DEMOLITION OF PAVEMENT | 533| | |------------|(FLEXIBLE) |---------| | |508 | | SY | | | | -------------------------------------------------------------------------------- |0230 | 27321|PROTECTIVE COVERING | 82| | |------------|EC-2 |---------| | |606 | | SY | | | | -------------------------------------------------------------------------------- A = PRICE ADJUSTMENT ITEM M = MAJOR ITEM S = SPECIALTY ITEM F = FUEL ADJUSTMENT ITEM P = PLAN QUANTITY E22-PSPPROP VIRGINIA DEPARTMENT OF TRANSPORTATION PAGE: 4 CONTRACT ID : CM108BRA39537 STATE PROJ NUM: 0613-084-6012,SR01 FEDERAL PROJ NUM:NONE ORDER NO. A34 DATE 01/08/08 SCHEDULE OF ITEMS REVISED CONTRACTOR :____________________________________________________________________ -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- |0240 | 27415|CHECK DAM(ROCK) TY. II | 9| | |------------| |---------| | |303 | | EA | | | | -------------------------------------------------------------------------------- |0250 | 27422|DEWATERING BASIN | 2| | |------------| |---------| | |303 | | EA | | | | -------------------------------------------------------------------------------- |0260 | 27430|SILTATION CONTROL | 96| | |------------|EXCAVATION |---------| | |303 | | CY | | | | -------------------------------------------------------------------------------- |0270 | 27505|TEMP. SILT FENCE | 500| | |------------| |---------| | |303 | | LF | | | | -------------------------------------------------------------------------------- M |0280 | 60404|CONCRETE CLASS A4 | 94| | |------------| |---------| | |404 | | CY | | | | -------------------------------------------------------------------------------- P |0290 | 60490|BRIDGE DECK GROOVING | 293| | |------------| |---------| | |404 | | SY | | | | -------------------------------------------------------------------------------- PA |0300 | 61705|EPOXY COATED REINF. | 21260| | |------------|STEEL * |---------| | |406 | | LB | | | | -------------------------------------------------------------------------------- AM |0310 | 61812|STR.STEEL PLATE GIRDER | 1| | |------------|ASTM A709 GRADE 50W |---------| | |407 | | LS | | | | -------------------------------------------------------------------------------- P |0320 | 62031|RAILING,KANSAS CORRAL | 203| | |------------|27" W/OUT CURB |---------| | |410 | | L.F. | | | | -------------------------------------------------------------------------------- P |0330 | 62534|BRIDGE SUPERSTRUCTURE | 28| | |------------|ELASTIC INCLUSION |---------| | |ATTD |(10" THICKNESS) |SY | | | | -------------------------------------------------------------------------------- |0340 | 66120|COFFERDAM | 2| | |------------| |---------| | |401 | | EA | | | | -------------------------------------------------------------------------------- |0350 | 67904|BRIDGE INCIDENTALS | 1| | ------------|TEMPORARY SHORING |---------| | |PLAN | |LS | | | | -------------------------------------------------------------------------------- A = PRICE ADJUSTMENT ITEM M = MAJOR ITEM S = SPECIALTY ITEM F = FUEL ADJUSTMENT ITEM P = PLAN QUANTITY E22-PSPPROP VIRGINIA DEPARTMENT OF TRANSPORTATION PAGE: 5 CONTRACT ID : CM108BRA39537 STATE PROJ NUM: 0613-084-6012,SR01 FEDERAL PROJ NUM:NONE ORDER NO. A34 DATE 01/08/08 SCHEDULE OF ITEMS REVISED CONTRACTOR :____________________________________________________________________ -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- |0360 | 68476|ENV.& WORK. PROTECTION | 1| | ------------|STR. NO. 6012 |---------| | |413 | |LS | | | | -------------------------------------------------------------------------------- |0370 | 68492|MATERIAL DISPOSAL | 1| | ------------|STR. NO. 6012, TY. B |---------| | |413 | |LS | | | | -------------------------------------------------------------------------------- |0380 | 68760|TRAF. BARRIER SERVICE | 108| | |------------|CONC. SINGLE FACE PAR. |---------| | |512 | | LF | | | | -------------------------------------------------------------------------------- |0390 | 68900|REM. PORT. OF EX. STR. | 1| | ------------|NO. 6012 |---------| | |413 | |LS | | | | -------------------------------------------------------------------------------- P |0400 | 69011|STRUCTURE EXCAVATION | 600| | |------------| |---------| | |401 | | CY | | | | -------------------------------------------------------------------------------- M |0410 | 69030|CONCRETE CLASS A3 | 180| | |------------| |---------| | |412 | | CY | | | | -------------------------------------------------------------------------------- A |0420 | 69100|REINF. STEEL | 9890| | |------------| |---------| | |412 406 | | LB | | | | -------------------------------------------------------------------------------- A |0430 | 69105|EPOXY COATED REINF. | 7100| | |------------|STEEL |---------| | |412 406 | | LB | | | | -------------------------------------------------------------------------------- | TOTAL ITEMS IN SECTION 0001 | | | -------------------------------------------------------------------------------- | TOTAL BID | | | -------------------------------------------------------------------------------- | | | | | | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- | | | | | | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- A = PRICE ADJUSTMENT ITEM M = MAJOR ITEM S = SPECIALTY ITEM F = FUEL ADJUSTMENT ITEM P = PLAN QUANTITY E22-PSPPROP VIRGINIA DEPARTMENT OF TRANSPORTATION PAGE: 2 CONTRACT ID : C00076725C07 STATE PROJ NUM: (FO) 0064-131-F11, C507 FEDERAL PROJ NUM:NH-064-3(456) ORDER NO. A35 DATE 01/08/08 SCHEDULE OF ITEMS REVISED CONTRACTOR :____________________________________________________________________ -------------------------------------------------------------------------------- MC | LINE| ITEM | ITEM | APP QTY.| UNIT PRICE | BID AMOUNT |------------| DESCRIPTION |---------|--------------|-------------- |SPEC NUMBER | | UNITS | DOLLARS|CTS | DOLLARS|CTS -------------------------------------------------------------------------------- | COMMON ITEMS -------------------------------------------------------------------------------- |0010 | 00100|MOBILIZATION | 1| | |------------| |---------| | |513 | | LS | | | | -------------------------------------------------------------------------------- |0020 | 00101|CONSTRUCTION SURVEYING | 1| | |------------| |---------| | |105 | | LS | | | | -------------------------------------------------------------------------------- |0030 | 00110|CLEARING AND GRUBBING | 1| | |------------| |---------| | |301 | | LS | | | | -------------------------------------------------------------------------------- |0040 | 00126|EARTHWORK | 1| | |------------| |---------| | |303 | | LS | | | | -------------------------------------------------------------------------------- |0060 | 13755|PRECAST CONC. SOUND | 74360| | |------------|BARR. WALL ABSORPTIVE |---------| | |519 ATTD | | SF | | | | -------------------------------------------------------------------------------- |0070 | 22501|FENCE FE-W1 | 12| | |------------| |---------| | |507 | | LF | | | | -------------------------------------------------------------------------------- |0080 | 22541|LINE BRACE UNIT | 2| | |------------|FE-W1,FE-W2 |---------| | |507 | | EA | | | | -------------------------------------------------------------------------------- |0090 | 22581|CORNER BRACE UNIT | 2| | |------------|FE-W1,FE-W2 |---------| | |507 | | EA | | | | -------------------------------------------------------------------------------- |0100 | 23501|FENCE FE-W1 (FABRIC | 48| | |------------|ONLY) |---------| | |ATTD | | LF | | | | -------------------------------------------------------------------------------- |0110 | 24160|CONSTRUCTION SIGNS | 82| | |------------| |---------| | |512 | | SF | | | | -------------------------------------------------------------------------------- |0120 | 24278|GROUP 2 CHANNELIZING | 240| | |------------|DEVICES |---------| | |512 | | DAY | | | | -------------------------------------------------------------------------------- A = PRICE ADJUSTMENT ITEM M = MAJOR ITEM S = SPECIALTY ITEM F = FUEL ADJUSTMENT ITEM P = PLAN QUANTITY E22-PSPPROP VIRGINIA DEPARTMENT OF TRANSPORTATION PAGE: 3 CONTRACT ID : C00076725C07 STATE PROJ NUM: (FO) 0064-131-F11, C507 FEDERAL PROJ NUM:NH-064-3(456) ORDER NO. A35 DATE 01/08/08 SCHEDULE OF ITEMS REVISED CONTRACTOR :____________________________________________________________________ -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- |0130 | 24290|TRAFFIC BARRIER | 2024| | |------------|SERVICE CONCRETE |---------| | |512 | | LF | | | | -------------------------------------------------------------------------------- |0140 | 27022|TOPSOIL CLASS B 2" | 2| | |------------| |---------| | |602 | | ACRE | | | | -------------------------------------------------------------------------------- |0150 | 27102|REGULAR SEED | 544| | |------------| |---------| | |603 | | LB | | | | -------------------------------------------------------------------------------- |0160 | 27103|OVERSEEDING | 340| | |------------| |---------| | |603 | | LB | | | | -------------------------------------------------------------------------------- |0170 | 27215|FERTILIZER(15-30-15) | 1| | |------------| |---------| | |603 | | TON | | | | -------------------------------------------------------------------------------- |0180 | 27250|LIME | 4| | |------------| |---------| | |603 | | TON | | | | -------------------------------------------------------------------------------- |0190 | 27321|PROTECTIVE COVERING | 388| | |------------|EC-2 |---------| | |606 | | SY | | | | -------------------------------------------------------------------------------- |0200 | 27410|CHECK DAM, ROCK TY. I | 7| | |------------| |---------| | |303 | | EA | | | | -------------------------------------------------------------------------------- |0210 | 27430|SILTATION CONTROL | 1368| | |------------|EXCAVATION |---------| | |303 | | CY | | | | -------------------------------------------------------------------------------- |0220 | 27506|TEMP. FILTER BARRIER | 7850| | |------------| |---------| | |303 | | LF | | | | -------------------------------------------------------------------------------- | TOTAL ITEMS IN SECTION 0001 | | | -------------------------------------------------------------------------------- | TOTAL BID | | | -------------------------------------------------------------------------------- A = PRICE ADJUSTMENT ITEM M = MAJOR ITEM S = SPECIALTY ITEM F = FUEL ADJUSTMENT ITEM P = PLAN QUANTITY E22-PSPPROP VIRGINIA DEPARTMENT OF TRANSPORTATION PAGE: 2 CONTRACT ID : C00084775N01 STATE PROJ NUM: (NFO)PM08-007-316, N501 FEDERAL PROJ NUM:NH-PM08(220) ORDER NO. A37 DATE 01/08/08 SCHEDULE OF ITEMS REVISED CONTRACTOR :____________________________________________________________________ -------------------------------------------------------------------------------- MC | LINE| ITEM | ITEM | APP QTY.| UNIT PRICE | BID AMOUNT |------------| DESCRIPTION |---------|--------------|-------------- |SPEC NUMBER | | UNITS | DOLLARS|CTS | DOLLARS|CTS -------------------------------------------------------------------------------- | COMMON ITEMS -------------------------------------------------------------------------------- |0010 | 10700|RUMBLE STRIP, ASPHALT | 44300| | |------------| |---------| | |ATTD | | LF | | | | -------------------------------------------------------------------------------- A |0020 | 10701|LIQUID ASPHALT COATING | 6547| | |------------| |---------| | |ATTD | | SY | | | | -------------------------------------------------------------------------------- A |0030 | 13290|GUARDRAIL GR-8 | 4988| | |------------|(NCHRP 350 TL-3) |---------| | |505 | | LF | | | | -------------------------------------------------------------------------------- A |0040 | 13292|GUARDRAIL GR-8A | 25| | |------------|(NCHRP 350 TL-3) |---------| | |505 | | LF | | | | -------------------------------------------------------------------------------- A |0050 | 13294|GUARDRAIL GR-8B | 25| | |------------|(NCHRP 350 TL-3) |---------| | |505 | | LF | | | | -------------------------------------------------------------------------------- A |0060 | 13310|GUARDRAIL TERMINAL | 250| | |------------|GR-6 (NCHRP 350) |---------| | |505 | | LF | | | | -------------------------------------------------------------------------------- A |0070 | 13315|GUARDRAIL TERMINAL | 9| | |------------|GR-11 |---------| | |505 | | EA | | | | -------------------------------------------------------------------------------- A |0080 | 13320|GUARDRAIL GR-2 | 10425| | |------------| |---------| | |505 | | LF | | | | -------------------------------------------------------------------------------- A |0090 | 13345|ALTERNATE BREAKAWAY | 2| | |------------|CABLE TERMINAL (GR-9) |---------| | |505 | | EA | | | | -------------------------------------------------------------------------------- |0100 | 13349|GUARDRAIL TERMINAL | 2| | |------------|SITE PREPARATION |---------| | |505 | | EA | | | | -------------------------------------------------------------------------------- A |0110 | 13359|GUARDRAIL TERMINAL | 5| | |------------|GR-8 TYPE II |---------| | |505 | | EA | | | | -------------------------------------------------------------------------------- A = PRICE ADJUSTMENT ITEM M = MAJOR ITEM S = SPECIALTY ITEM F = FUEL ADJUSTMENT ITEM P = PLAN QUANTITY E22-PSPPROP VIRGINIA DEPARTMENT OF TRANSPORTATION PAGE: 3 CONTRACT ID : C00084775N01 STATE PROJ NUM: (NFO)PM08-007-316, N501 FEDERAL PROJ NUM:NH-PM08(220) ORDER NO. A37 DATE 01/08/08 SCHEDULE OF ITEMS REVISED CONTRACTOR :____________________________________________________________________ -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- |0120 | 13401|GUARDRAIL | 1000| | |------------|GUARDRAIL BLOCKOUTS |---------| | |ATTD | |EA | | | | -------------------------------------------------------------------------------- A |0130 | 16325|ASPHALT CONCRETE | 154| | |------------|SM-12.5A |---------| | |315 | |TON | | | | -------------------------------------------------------------------------------- A |0140 | 16352|ASPH. CON. TY. | 600| | |------------|SM-12.5ASL(SPOT LEVEL) |---------| | |315 | | TON | | | | -------------------------------------------------------------------------------- A |0150 | 16355|ASPHALT CONCRETE | 9151| | |------------|TY. SM-12.5D |---------| | |315 | | TON | | | | -------------------------------------------------------------------------------- |0160 | 16386|FLEXIBLE PAVEMENT | 166390| | |------------|PLANING |---------| | |515 | | SY | | | | -------------------------------------------------------------------------------- |0170 | 24601|REMOVE EXIST. GUARDRAIL| 11050| | |------------|.... |---------| | |510 | |LF | | | | -------------------------------------------------------------------------------- |0180 | 54075|TYPE B CLASS VI PAVE. | 2350| | |------------|LINE MARKING 4" |---------| | |ATTD704 | | LF | | | | -------------------------------------------------------------------------------- |0190 | 54076|TYPE B CLASS VI PAVE. | 55863| | |------------|LINE MARKING 6" |---------| | |ATTD704 | | LF | | | | -------------------------------------------------------------------------------- |0200 | 54077|TYPE B CLASS VI PAVE. | 1480| | |------------|LINE MARKING 8" |---------| | |ATTD704 | | LF | | | | -------------------------------------------------------------------------------- |0210 | 54100|PAVEMENT MARKING | 750| | |------------|6" CONTRAST TAPE |---------| | |ATTD | |LF | | | | -------------------------------------------------------------------------------- |0220 | 54217|SNOW PLOW. RAISED | 471| | |------------|PAVE. MARKER ASPH.CONC |---------| | |704 | | EA | | | | -------------------------------------------------------------------------------- | TOTAL ITEMS IN SECTION 0001 | | | -------------------------------------------------------------------------------- | TOTAL BID | | | -------------------------------------------------------------------------------- A = PRICE ADJUSTMENT ITEM M = MAJOR ITEM S = SPECIALTY ITEM F = FUEL ADJUSTMENT ITEM P = PLAN QUANTITY E22-PSPPROP VIRGINIA DEPARTMENT OF TRANSPORTATION PAGE: 2 CONTRACT ID : C00084806N01 STATE PROJ NUM: (NFO)PM08-082-319, N501 FEDERAL PROJ NUM:NH-PM08(221) ORDER NO. A38 DATE 01/08/08 SCHEDULE OF ITEMS REVISED CONTRACTOR :____________________________________________________________________ -------------------------------------------------------------------------------- MC | LINE| ITEM | ITEM | APP QTY.| UNIT PRICE | BID AMOUNT |------------| DESCRIPTION |---------|--------------|-------------- |SPEC NUMBER | | UNITS | DOLLARS|CTS | DOLLARS|CTS -------------------------------------------------------------------------------- | COMMON ITEMS -------------------------------------------------------------------------------- | | | | .| | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- | TOTAL ITEMS IN SECTION 0001 | | | -------------------------------------------------------------------------------- | TOTAL BID | | | -------------------------------------------------------------------------------- | | | | | | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- | | | | | | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- | | | | | | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- | | | | | | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- | | | | | | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- | | | | | | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- | | | | | | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- | | | | | | |------------| |---------| | | | | | | | | -------------------------------------------------------------------------------- A = PRICE ADJUSTMENT ITEM M = MAJOR ITEM S = SPECIALTY ITEM F = FUEL ADJUSTMENT ITEM P = PLAN QUANTITY E22-PSPPROP VIRGINIA DEPARTMENT OF TRANSPORTATION PAGE: 2 CONTRACT ID : C00084813N01 STATE PROJ NUM: (NFO)PM08-093-314, N501 FEDERAL PROJ NUM:NHS-PM08(222) ORDER NO. A39 DATE 01/08/08 SCHEDULE OF ITEMS REVISED CONTRACTOR :____________________________________________________________________ -------------------------------------------------------------------------------- MC | LINE| ITEM | ITEM | APP QTY.| UNIT PRICE | BID AMOUNT |------------| DESCRIPTION |---------|--------------|-------------- |SPEC NUMBER | | UNITS | DOLLARS|CTS | DOLLARS|CTS -------------------------------------------------------------------------------- | COMMON ITEMS -------------------------------------------------------------------------------- |0010 | 10700|RUMBLE STRIP, ASPHALT | 70183| | |------------| |---------| | |ATTD | | LF | | | | -------------------------------------------------------------------------------- A |0020 | 10701|LIQUID ASPHALT COATING | 10372| | |------------| |---------| | |ATTD | | SY | | | | -------------------------------------------------------------------------------- A |0030 | 13310|GUARDRAIL TERMINAL | 25| | |------------|GR-6 (NCHRP 350) |---------| | |505 | | LF | | | | -------------------------------------------------------------------------------- A |0040 | 13315|GUARDRAIL TERMINAL | 1| | |------------|GR-11 |---------| | |505 | | EA | | | | -------------------------------------------------------------------------------- A |0050 | 13320|GUARDRAIL GR-2 | 1325| | |------------| |---------| | |505 | | LF | | | | -------------------------------------------------------------------------------- A |0060 | 13335|GUARDRAIL GR-3 | 750| | |------------| |---------| | |505 | | LF | | | | -------------------------------------------------------------------------------- A |0070 | 13336|GUARDRAIL TERMINAL | 5| | |------------|GR-3 |---------| | |505 | | EA | | | | -------------------------------------------------------------------------------- A |0080 | 13345|ALTERNATE BREAKAWAY | 1| | |------------|CABLE TERMINAL (GR-9) |---------| | |505 | | EA | | | | -------------------------------------------------------------------------------- |0090 | 13349|GUARDRAIL TERMINAL | 1| | |------------|SITE PREPARATION |---------| | |505 | | EA | | | | -------------------------------------------------------------------------------- |0100 | 13401