General Scope:

  • Expand the Hampton Roads Bridge-Tunnel from Hampton to Norfolk
  • Provide 6 Lane Capacity to I-64 from I-664 to I-564

Project Cost Estimate:

  • $3.3 billion (2016$)

Project Schedule:

  • Contract Award Projected in 2019
  • Project Completion Expected in 2024

Current Status:

  • Numerous studies and surveys are underway to refine the project scope:
    • Corridor Survey
    • Geotechnical Studies
    • Wetland Delineation
    • Benthic Survey
    • Wildlife Studies
    • Cultural Resources Survey
    • Navigational Study
    • Hazardous Material Investigation
    • Traffic Operations Modeling