VDOT FINISHES FISCAL YEAR 2005 WITH MORE PROJECTS COMPLETED ON TIME AND ON BUDGET
Fourth quarter report card released today


View full report online


RICHMOND – The Virginia Department of Transportation (VDOT) completed 75 percent of its construction contracts on time and 78 percent within budget for fiscal year 2005 (June 30, 2004 – July 1, 2005). That compares to 27 percent on-time and 65 percent within-budget performance two years ago.

“The sound business practices implemented under Governor Mark Warner’s leadership are achieving clear results,” said Transportation Secretary Pierce Homer. “As today’s report illustrates, VDOT is operating much more efficiently than just a few years ago.”

“We’ve seen a steady turnaround in our performance by setting clear goals and coming together as an agency to meet them,” said Acting Commissioner Gregory A. Whirley. “While we have made tremendous progress, it is important that additional work be done to increase accountability and improve business operations.”

VDOT’s performance targets for fiscal year 2006 is to complete 65 percent of construction contracts and 75 percent of maintenance projects on time, and to complete 80 percent of construction contracts and 90 percent of maintenance projects within budget.

Report Card Results:

Deadlines:

Construction contracts completed on time

FY 2005 – 75 percent (against a target of 60%)
FY 2004 – 36 percent
FY 2003 – 27 percent

Maintenance contracts completed on time

FY 2005 – 74 percent (against a target of 70%)
FY 2004 – 51 percent
FY 2003 – 38 percent

Budgets:

Construction contracts completed within budget

FY 2005 – 78 percent (against a target of 80%)
FY 2004 – 73 percent
FY 2003 – 65 percent

Maintenance contracts completed within budget

FY 2005 – 80 percent (against a target of 90%)
FY 2004 – 81 percent
FY 2003 – 80 percent