PILE DRIVING FOR ELIZABETH RIVER TUNNELS PROJECT UNDERWAY IN NORFOLK

PORTSMOUTH – The sounds of progress continue throughout the Elizabeth River Tunnels Project this week as crews drive sheet piles to support construction of the Norfolk Approach to the new Midtown Tunnel.

Crews are driving more than 500 pairs of sheets up to 70 feet deep near the Midtown Tunnel portal in Norfolk. Nearby residents and businesses may see and/or hear the operations, which are not expected to exceed the City of Norfolk’s noise ordinance. Work hours are Monday through Saturday, 7 a.m. to 5:30 p.m. now, through winter 2013.  

Fall 2013, crews will begin driving precast concrete piles that range from 18” to 24” square, up to 85 feet in length. They will serve as a vital foundation component of the new approach.

Headquartered in Portsmouth, Virginia, Elizabeth River Crossings OpCo, LLC, is the private partner of the Virginia Department of Transportation for the design, construction, finance, operations and maintenance of the Elizabeth River Tunnels Project. For more information on the Elizabeth River Tunnels Project, visit www.DriveERT.com. Follow us on Twitter at https://twitter.com/DriveERT.

###



Information in VDOT news releases was accurate at the time the release was published. For the most current information about projects or programs, please visit the project or program Web pages. You may find those by searching by keyword in the search Virginia DOT box above.