| RELEASE: CONTACT: |
IMMEDIATE Mike Salmon 703-383-2850 |
NOVA-31330 July 30, 2008 |
VDOT Begins Utility Relocation in Gainesville
First Step in Major Road Improvements
The two-year utility relocation and building demolition phase precedes the four-year construction project scheduled to begin in spring 2011 that will:
- · elevate Linton Hall Road over Route 29;
- · elevate Route 29 over the railroad tracks;
- · construct bridges over Gallerher Road and the railroad tracks at Route 29;
- · add a lane on Route 29 from I-66 to Virginia Oaks Drive; and,
- · build new ramps to facilitate traffic movements at Route 29 and Linton Hall Road intersection.
Utility work will be on the north side of Route 55 from the intersection of Route 29 to Gallerher Road. VDOT is building a duct bank to house Verizon, MCI and Quest Communications lines. In addition, Columbia Gas is installing a new gas line adjacent to the duct bank.
Motorists can expect occasional lane closures associated with the utility relocation work along Route 55 during the week from 9 a.m. to 3 p.m., but not along Route 29 during this phase. Updates will be provided as work progresses. In September, Dominion Power is scheduled to relocate electric lines along Route 55.
Originally construction was scheduled to begin in 2013, but under direction of Governor Kaine, the timeframe was pushed up to 2010 by phasing in property acquisition and utility relocation.
##
Tweet
Information in VDOT news releases was accurate at the time the release was published. For the most current information about projects or programs, please visit the project or program Web pages. You may find those by searching by keyword in the search Virginia DOT box above.





















