LUCASVILLE ROAD NOW OPEN TO TRAFFIC

MANASSAS ― At 1 p.m. today the Virginia Department of Transportation (VDOT) re-opened Lucasville Road in Manassas, five weeks ahead of schedule.

The $3.2 million project included raising the roadway’s profile and installing a quadruple box culvert to improve drainage and mitigate flooding. The two-lane road now has curb and gutter, and a sidewalk on the east side of the road.

See VDOT's project page for more details.



Information in VDOT news releases was accurate at the time the release was published. For the most current information about projects or programs, please visit the project or program Web pages. You may find those by searching by keyword in the search Virginia DOT box above.