Place holder
Travel Center
Place holder
News
Place holder
Info Center
Place holder
Business Center
Place holder
Programs
Place holder
Projects
Place holder
About
Place holder
Jobs
Place holder
Sitemap
Place holder
Call 1-800-FOR-ROAD



RELEASE:

CONTACT:
IMMEDIATE

Jeff Caldwell (804) 786-2715
Jeffrey.Caldwell@VDOT.Virginia.gov
Donna Purcell Mayes (804) 786-2717
CO-0717

May 17, 2007



VDOT MEETING GOALS FOR ON-TIME AND ON-BUDGET PROJECTS
Third report for fiscal year 2007 shows persistent improvement

RICHMOND — The Virginia Department of Transportation (VDOT) continues tracking progress to exceed all construction and maintenance deadline, budget and quality targets through the third quarter of fiscal year 2007, running from Jan. 1 through March 31, 2007. The results were released as part of the department’s quarterly report issued this week. Click to download the latest Quarterly Report


“Once again, this report shows that our unrelenting effort to deliver projects on-time and on-budget is changing our business,” said Commissioner David S. Ekern. “As we move forward into the next fiscal year, we will keep our focus on schedules and budgets while adding additional performance measures to drive improvements in customer satisfaction, financial accountability, safety and VDOT management. These quarterly reports and our Dashboard will tell more of the story about the work of this $3.8 billion mobility corporation.”

Report Card Results:

Deadlines:

Construction contracts completed on time (FY 2007 goal, 70 percent)

  • Through the third quarter of FY2007 – 89 percent

  • Through the third of FY 2006 – 83 percent

  • Through the third of FY 2005 – 74 percent


Maintenance contracts completed on time (FY 2007 goal, 75 percent)

  • Through the third quarter of FY 2007 – 78 percent

  • Through the third quarter of FY 2006 – 78 percent

  • Through the third quarter of FY 2005 – 77 percent


Budgets:

Construction contracts completed within budget (FY 2007 goal, 80 percent)

  • Through the third quarter of FY 2007 – 93 percent

  • Through the third quarter of FY 2006 – 88 percent

  • Through the third quarter of FY 2005 – 81 percent


Maintenance contracts completed within budget (FY 2007 goal, 90 percent)

  • Through the third quarter of FY 2007 – 95 percent

  • Through the third quarter of FY 2006 – 90 percent

  • Through the third quarter of FY 2005 – 83 percent


Statewide Construction Quality Compliance: (FY 2007 goal, 91 percent)

  • Through the third quarter of FY 2007 — 91.6 percent

  • Results for FY 2006 – 90.3 percent (data not previously broken down by quarter)


The full report is available online at VirginiaDOT.org/info/ctb-qtrlyrpt.asp, or click the image above.

“It is too soon to celebrate achievement of our goals in all areas for this entire year,” Ekern said. “During the next quarter, the pressure will be on to achieve all five goals for the entire fiscal year 2007 and deliver the best possible transportation system to our customers, the citizens of Virginia.”

In a major effort to provide citizen access to VDOT’s performance measurements, the agency began releasing quarterly reports and launched its Dashboard in 2003. The Dashboard is an online system that provides the latest status on construction, maintenance, operations, safety, finance and environmental compliance.

For more information about all of VDOT’s projects and programs or to view the VDOT Dashboard, visit VirginiaDOT.org.

(END)







Information in VDOT news releases was accurate at the time the release was published. For the most current information about projects or programs, please visit the project or program Web pages. You may find those by searching by keyword in the search Virginia DOT box above.



Page last modified: Jan. 15, 2008