RELEASE:

CONTACT:
IMMEDIATE

Sandy Myers 540-332-9201
Sandy.Myers@vdot.virginia.gov
540-292-2500 (cell)
Ken Slack 540-332-9264
Ken.Slack@vdot.virginia.gov
540-414-5670 (cell)
STA10-161

Oct. 1, 2010



TRAFFIC ALERT FOR WEEK OF OCTOBER 4-8, 2010
Highway work zones in the Staunton District

The following is a list of highway work that might affect traffic in the Staunton transportation district during the coming weeks. The Staunton district is comprised of 11 counties, Alleghany, Bath, Rockbridge, Augusta, Highland, Rockingham, Shenandoah, Frederick, Page, Warren and Clarke. Work scheduled is subject to change due to inclement weather and material supplies. Motorists are advised to watch for slow-moving tractors during mowing operations. Also, when traveling through a work zone, be alert to periodic changes in traffic patterns and lane closures.

 

(NEW) _ Indicates a new or revised entry since last week’s report.

 

ALLEGHANY COUNTY

Interstate 64  

* Mile marker 0 to 41, eastbound and westbound – Debris removal and drainage repair. Shoulder closed, Monday, Wednesday and Friday, 7:30 a.m. to 3 p.m.

* Mile marker 18.5 to 24.5, westbound and eastbound – Left lane closures. Median barrier construction installation project.  Long-term left lane closures with concrete barrier. Median barrier construction installation project. Department of Motor Vehicles (DMV) oversized load note: For week of Oct. 4 left lane closures eastbound and westbound for entire work zone around Oct. 6.  This is weather dependent.  Traffic pattern adjustments should be complete on I-64 westbound for drainage item installation in median.  Wide loads up to 15 feet will be able to proceed through the work zone in eastbound lanes and beginning Oct. 6 also in the westbound lanes.

* Mile marker 23 to 20, westbound – Right shoulder closure. Left lane closures eastbound and westbound for entire work zone around Oct. 6.  This is weather dependent.

 

Primary Roads                                       

* Route F-205 (Irvine Farm Road) – Flagging operations for I-64 median barrier project work.

 

Secondary Roads

* Route 616 (Rich Patch Road) – Box culvert replacement at Karnes Creek. Single-lane traffic with stop and proceed sign. Roadway is restricted to a 10-foot width. Single-lane traffic will be in place 24 hours-a-day until mid-November. Work zone will be active on weekdays from 7 a.m. until 7 p.m. Motorists should use extreme caution in this area and watch for construction vehicles.

* Route 1101 (Winterberry Avenue) – Flagging operations for I-64 median barrier project work.

* Route 1011 – Bridge replacement in Selma area between Route 1002 and Route 1003. Road will be closed Monday to Thursday. Detour signs in place.

* Various locations – Mowing and patching, Monday to Friday, 7:30 a.m. to 3:30 p.m.

 

 

BATH COUNTY

Primary Roads

No lane closures reported.

 

Secondary Roads

* Route 627 (Scotchtown Draft Road) – Pipe work.  Road closed from Oct. 4 from 8 a.m. to 5 p.m.  This is .6 mile east of Route 678 (Indian Draft Road) and approximately two miles west of Route 629 (Deerfield Road).  Signs will be posted.  Motorists should plan alternate travel routes.

* Various roads – Mowing and pipe work. Single-lane traffic controlled by flaggers, Monday to Friday, 7 a.m. to 3:30 p.m.

 

 

ROCKBRIDGE COUNTY

Interstate 64

* Mile marker 41 to 56 eastbound and westbound – Debris removal, Monday, Wednesday and Friday, 7 a.m. to 3:30 p.m.

 

Interstate 81

* Mile marker 173 to 205 northbound and southbound – Debris removal, Monday, Wednesday and Friday, 7 a.m. to 3:30 p.m.

* (UPDATE) Blasting will occur on Oct. 5 and Oct. 7 at 1 p.m.  The blasting locations will be on I-81 between mile markers 197 to 199.  Signs are posted in this area. Both northbound and southbound lanes will have a rolling mobile lane closure. 

 

Nighttime northbound lane closures will be on Oct. 4 and Oct. 5.  The closure will be from 8:30 p.m. to 6:30 a.m. each evening. All northbound lanes will be closed between exit 195 and exit 200 and the left southbound lane will be closed from mile marker 198.8 to 198.6. The northbound traffic detour takes traffic off I-81 at exit 195 in the Lexington and Timber Ridge area onto Route 11 north and then onto Route 710 west to I-81.  Traffic will be rejoining I-81 at exit 200, which is at Route 710 in the Fairfield area.  This closure is for setting of structural steel for the Route 712 Bridge.

 

Additional southbound lane closures are planned for Oct. 6 and Oct. 7. Both southbound lanes will be closed between exit 200 and exit 195 from 8:30 p.m. to 6:30 a.m.  The southbound traffic detour takes traffic off I-81 at exit 200 in the Fairfield area onto Route 710 east to Route 11 south and then rejoining I-81 at exit 195 in the Lexington and Timber Ridge area. This closure is for setting of structural steel for the Route 712 Bridge. 

 

Primary Roads

* Route 130 – Bridge work in Glasgow.  Be alert for new traffic pattern using new bridge.  Shoulder closures 7 a.m. to 5 p.m. Monday to Friday.  Watch for construction traffic in this work zone.

* Route 501 (Glasgow Highway) – Concrete culvert repairs at 0.04 mile from Route 792 south to 0.11 mile Route 792 north. Single-lane traffic, Monday to Friday, 7 a.m. to 7 p.m. Estimated completion is Oct. 1.

 

Secondary Roads

* Route 603 – Bridges over Irish Creek. Paving and guardrail work from 1.40 miles east of Route 608 and 5.45 miles east of Route 608. Flagger traffic control, Monday to Friday, 7 a.m. to 7 p.m.

* (NEW) Route 716 (Timber Ridge Road) – Bridge work .08 mile east of Route 754 to Route 608 near Cornwall.  Road closed Monday to Thursday, 8 a.m. to 4:30 p.m. from Oct. 4 to Oct. 28.

* (NEW) Route 717 (Goose Creek Road) – Pipe and ditch work.  Work zone is .2 mile east of Route 724 to .88 mile east of Route 721.  Flagger traffic control, Monday to Friday, 8 a.m. to 4:30 p.m.

* Various roads – Brush cutting, tractor mowing, grading and shoulder repair mowing, Monday to Friday, 7 a.m. to 3:30 p.m.

 

 

HIGHLAND COUNTY

Primary Roads

No lane closures reported.

 

Secondary Roads

* Route 604 – Pipe work, Monday to Friday, 7 a.m. to 3:30 p.m. Flagger traffic control.

* (NEW) Route 607 – Mowing, Monday to Friday, 7 a.m. to 3:30 p.m.

* (NEW) Various roads – Tar and gravel placement Monday to Friday, 7 a.m. to 3:30 p.m.

 

 

AUGUSTA COUNTY 

Interstate 64

* (NEW) Mile marker 87 to 99, eastbound and westbound – Vegetation management.  Mobile lane closure, Monday to Friday.

* (NEW) Mile marker 102.5 to 94.9, eastbound – Guardrail work, Monday to Friday.

 

Interstate 81

* (NEW) Mile marker 219, northbound and southbound – Bridge work.  Bridge over Folly Mills Creek.  Shoulder closures Monday to Friday, 7 a.m. to 7 p.m.

 

Primary Roads

* Route 42 – Mossy Creek project. Roadway relocation and bridge replacement with box culvert. Work will occur from 0.63 mile south of Rockingham County line to 0.90 mile south of Rockingham County line. Expect minor delays Monday to Friday, 7 a.m. to 5:30 p.m. Two lanes of roadway will be maintained.  Completion is July 20, 2011.

* Churchville Avenue (Route 250, Staunton), eastbound – Road reconstruction activities. North Central Avenue is open to traffic. No left turn will be allowed from Churchville Avenue onto North Lewis Street. North Lewis Street is open to northbound traffic only. The eastbound lane will be closed from North Augusta Street (Route 11) to Albemarle Avenue 24 hours-a-day, seven days-a-week. The pedestrian detour is from North Augusta Street to North Lewis Street. Signs are posted.

Expect intermittent delays from North Augusta Street to Albemarle Avenue due to utility installation work. Intermittent flagger traffic control for work in westbound lane. Speed limit in the project area reduced to 25 miles-per-hour. Four recommended detours for eastbound Churchville Avenue traffic heading into Staunton business district from Route 262/Route 250 interchange are to North Augusta Street:

  • Take Route 250 and turn right onto Grubert Avenue and then turning left onto West Beverly Street, which intersects with North Augusta Street.
  • Take Route 250 and turn right onto Thornrose Avenue and then turning left on to West Beverly Street, which intersects with North Augusta Street.
  • Take Churchville Avenue and turn left onto Springhill Road to Route 262. Turn right onto Route 262 north to the Route 11 intersection. Turn right onto Route 11 and take Route 11 bypass (Commerce Road) into Staunton.

At the Route 262/Route 250 interchange – take Route 262 north to the Route 11 intersection. Turn right onto Route 11 and take Route 11 bypass (Commerce Road) into Staunton.

* Route 256 (Weyers Cave Road) – Grading, slope and turn lane work from 800-feet north of Route 11 (Lee Jackson Highway). Right shoulder closures, Monday to Friday, 7 a.m. to 5 p.m.

 

Secondary Roads

* Route 659 (Payton Hill Road) – Rural rustic project from Route 657 (Indian Ridge Road) to Route 11 (Lee Jackson Highway). Road closed, Monday to Friday, 7 a.m. to 5 p.m. Estimated completion is Oct. 15.

* Route 682 (McKinley Road) – Bridge work.  Road closed.  Work is from Route 679 (Campbell Hollow Road) to Route 252 (Middlebrook Road).  Estimated completion is Oct. 15.

* Route 694 (Swartzel Shop Road) – Rustic road construction from Route 686 (Hill Top Drive) to Route 340 (Stuarts Draft Highway). Road closed 7 a.m. to 5 p.m., Monday to Friday.

* Route 699 – Paving from Route 646 to 0.09 mile south of intersection of Route 646. Intersection relocation project to improve sight distance. Flagger traffic control, Monday to Saturday, 7 a.m. to 8 p.m.

* Route 746 – Road reconstruction with flaggers controlling traffic from Route 745 to Route 616.

* Route 835 (Varner Road) – Cross pipe installation and rustic road widening project from Route 728 (Stover Shop Road) to Route 736 (Union Church Road). Road closed, 7:30 a.m. to 4 p.m., Sept 13 to Oct. 29.

 

 

ROCKINGHAM COUNTY 

Interstate 81

* Mile marker 237 to 263, northbound and southbound – Debris removal, sign repairs and patching. Monday to Friday, 9 a.m. to 4 p.m.  Asphalt patch will have mobile lane closures, Tuesday and Wednesday, 8 p.m. to 7 a.m.

 

Primary Roads

* Stone Spring Road – Erickson Avenue/Stone Spring Road Connector Project from the Route 11 intersection to the Port Republic Road intersection. Lane and shoulder closures, daily, 8 a.m. to 5 p.m. Estimated completion is spring 2013.

* Route 33 (East Market Street) westbound bridge overpass– Bridge deck repairs in the vicinity of I-81 exit 247. The on-ramp for eastbound Route 33 traffic headed northbound on I-81 will be closed. Also the exit ramp for I-81 northbound traffic headed to Route 33 westbound will be closed.  The closures will begin on Oct. 4 and occur on weekdays from 8 p.m. to 7 a.m.  This work is expected to finish on Oct. 7. Motorists should follow detour signs.  Information about the closure and detour will be available by calling 511 or visiting the 511 website at www.511Virginia.org.

* Route 42 (Warm Springs Pike) – Aerial and buried optic cable work from Bridgewater Town limits and Route 42 south to Augusta County line. Right shoulder closure, Tuesday to Friday, 8 a.m. to 5 p.m.

* Route 253 (Port Republic Road) – Aerial and buried optic cable work from Route 825 (South River Road) to Route 655 (Lawyer Road). Right shoulder closure, Tuesday to Friday, 8 a.m. to 5 p.m.

* Route 253 (Port Republic Road) – Road widening project from Route 704 (Boyers Road) to Harrisonburg City limits. Motorists should be alert for a traffic pattern change on Oct. 7. Southbound traffic at the Harrisonburg city limits will be shifted to the right onto the newly constructed roadway.  Just before the Southeast Connector intersection, traffic will be moved to the left and rejoin the existing roadway.  Northbound traffic, just past the Southeast Connector, will shift to the left.  Prior to entering the Harrisonburg city limits, traffic will be guided to the right and return to the existing roadway. All work is subject to change and weather permitting.

* Various roads – Pipe installation, patching, brush cutting, shoulder repairs, ditching and grading.

 

Secondary Roads 

* Route 613 (Jordan Hill Road) – Road widening and drainage work from Route 729 (Campbell Road) to Augusta County line. Intermittent shoulder closures.

* Route 726 (Erickson Avenue) – Road work on Route 33 (Rawley Pike) and Route 726. Intermittent lane closures with flaggers controlling traffic, Tuesday to Friday, 8 a.m. to 5 p.m.

* Route 800 (Long Meadow Drive) – Columbia Gas work from Route 800 (Lone Pine Road) to Route 619 (Wampler Road). Monday to Friday, 8 a.m. to 5 p.m. Intermittent lane and shoulder closure with flagger traffic control.

* Route 800 (American Legion Drive) – Columbia Gas work from Route 801 (Holsinger Road) to end of state maintenance. Monday to Friday, 8 a.m. to 5 p.m. Intermittent lane and shoulder closure with flagger traffic control.

* Route 801 (Holsinger Road) – Columbia Gas work from Route 800 (American Legion Drive) to Route 619 (Wampler Road). Monday to Friday, 8 a.m. to 5 p.m. Intermittent lane and shoulder closure with flagger traffic control.

* Route 820 (Bergton Road) – Motorists should be alert for travel delays of up to 20 minutes for road construction and slope work. Work zone is 1.10 miles to 0.30 mile west of Route 259 (Brocks Gap Road). Construction in this section will be controlled by temporary traffic signals 24 hours-a-day, Aug. 16 to Oct. 16. The signals will be located at both ends of the construction area. Single-lane closures with flagger traffic control, Monday to Saturday 24 hours-a-day as needed. Motorists are urged to drive with caution in the work zone and to only proceed when a green light is present. Blasting operations will also occur Monday to Friday, 9 a.m. to 2 p.m. Delays up to one hour should be expected during these times. Estimated completion is Nov. 2010.

* Route 890 (Buckley Road) – Columbia Gas work from Route 619 (Piney Woods Road) to end of state maintenance. Monday to Friday, 8 a.m. to 5 p.m. Intermittent lane and shoulder closure with flagger traffic control.

* Route 955 (Jackson’s Way) – Bridge superstructure replacement on the Madison Run Bridge from 1.40 mile west of Route 340. Road closed, Sept. 20 to late October. Suggested detour:  Motorists wishing to access Route 955 west of the bridge should use the Route 253 (Port Republic Road) intersection with Route 955. Motorists wishing to access Route 955 east of the bridge should use the Route 340 intersection with Route 955.

* Various roads – Pipe installation, patching, brush cutting, shoulder repairs, ditching and grading.

 

 

PAGE COUNTY

Primary Road

* (NEW) Route 211 eastbound and westbound – Spot leveling from Shenandoah National Park Headquarters to Skyline Drive, Monday to Friday, 8 a.m. to 4 p.m.  Flagger traffic control.  Completion is Oct. 22.

* Various roads – Pipe installation, patching, brush cutting, shoulder repairs, ditching and grading. Monday to Friday, 7 a.m. to 3:30 p.m.

 

Secondary Roads

* Various roads – Pipe installation, patching, brush cutting, shoulder repairs, ditching and grading. Monday to Friday, 7 a.m. to 3:30 p.m.

 

 

SHENANDOAH COUNTY

Interstate 81

* Mile marker 263 to 298, northbound and southbound – Debris removal, sign repairs, and asphalt patching.  Monday to Friday, 9 a.m. to 4 p.m. Asphalt patching will have mobile lane closure Wednesday and Thursday, 8 p.m. to 7 a.m.

 

Primary Roads

No lane closures reported.

 

Secondary Roads

* (NEW) Route 675 – Bridge work.  Bridge over North Fork of the Shenandoah River located .25 mile east of Edinburg town limits.  Single lane traffic, Monday to Friday, 7 a.m. to 7 p.m.

* Route 744 (Deer Rapids) – Bridge over Shenandoah River. Bridge work from 0.30-mile east of Route 648 to 0.45-mile east of Route 648. Traffic controlled by flaggers as needed during daylight hours, Monday to Friday. Estimated completion is April 14, 2011.

* (NEW) Various roads – Patching, brush cutting and mowing.

 

FREDERICK COUNTY

Interstate 81

* Mile marker 300 to 324, northbound and southbound – Debris removal, shoulder repair, sign repairs, and asphalt patching.  Monday to Friday, 9 a.m. to 4 p.m. Asphalt patching will have mobile lane closure Wednesday and Thursday, 8 p.m. to 7 a.m.

 

Primary Roads

* Route 11 – Line painting from Route 1129 to Winchester City limits. Flagger traffic control, Sunday to Friday morning, 7 p.m. to 6 a.m. Estimated completion is Oct. 15.

* Route 11 (Martinsburg Pike) – Traffic signal construction at Route 672 (Hopewell Road/Brucetown Road).  Intermittent lane closures from Sept. 27 to Oct. 21.  Work is Monday to Thursday, 7 a.m. to 5:30 p.m.

* Route 277 (Fairfax Pike) – Line painting operations from Route 719 to Route 11. Flagger traffic control, Sunday to Friday, 7 p.m. to 6 a.m. Estimated completion is Oct. 15.

* Route 522, southbound – Paving from West Virginia Sate line to 0.02 mile south of Route 692. Alternating lane closures, Monday to Friday, 7 a.m. to 5 p.m. Estimated completion is Oct. 15.

* Route 522, northbound – Paving from 0.45 mile north of Route 681 to 0.52 mile north of Route 699. Alternating lane closures, Monday to Friday, 7 a.m. to 5 p.m. Estimated completion is Oct. 15.

* Route 522 – Intersection improvement at Route 642 (Tasker Road) including additional turn lane and signal installations.  Lane closures and lane shifts during construction.  Work is Monday to Friday, 7 a.m. to 5 p.m.  Completion is spring 2011.

* (NEW) Various roads – Mowing.

 

Secondary Roads

* Route 671 – Bridge repairs on bridge over Back Creek from 1.45 miles east of Route 681 to 0.03 mile west of Route 741. Single-lane traffic with flagger traffic control.

* (NEW) Various roads – Patching and mowing.

 

 

CLARKE COUNTY

Primary Roads

* (NEW) Route7 northbound and southbound – Spot leveling at various locations, Monday to Friday, 8 a.m. to 4 p.m. Flagger traffic control. Completion is Oct. 22.

* Route 50, westbound – Bridge deck maintenance on bridge over Shenandoah River from 0.10 mile west of Route 638 to 0.25 mile east of Route 622. Single-lane traffic, Monday to Friday, 7 a.m. to 5 p.m.

* (NEW) Route 340 northbound and southbound – Spot leveling at various locations, Monday to Friday, 8 a.m. to 4 p.m. Flagger traffic control. Completion is Oct. 22.

 

 

Secondary Roads

* (NEW) Route 723 (East Main Street/Millwood Road/West Main Street/Old Winchester Road) eastbound and westbound lanes – Boyce Centennial Celebration.  Roads closed from Route 655 (Ginns Road) to Route 255 (Bishop Meade Road), Oct. 2 from 9 a.m. to 7 p.m.  Sheriff’s department will control traffic and implement detour if needed.  Motorists should drive with caution and expect congestion.

* (NEW) Various roads – Mowing, brush cutting and scraping.

 

WARREN COUNTY

Interstate 66

* Mile marker 0 to 13, eastbound and westbound – Debris removal, shoulder repair and asphalt patching. Monday to Friday, 9 a.m. to 4 p.m.  Asphalt patching will have mobile lane closure Wednesday and Thursday, 8 p.m. to 7 a.m.

* (NEW) Mile marker 3 to 4.5 eastbound – Pavement patching work. The right eastbound lane will be closed from Oct. 4 and Oct. 5 from 8 a.m. to 8 p.m.

 

Interstate 81

* Mile marker 298 to 300, northbound and southbound – Debris removal. Monday to Friday, 9 a.m. to 4 p.m.

 

Primary Roads

* (NEW) Route 340 northbound and southbound – Spot leveling at various locations, Monday to Friday, 8 a.m. to 4 p.m. Flagger traffic control. Completion is Oct. 22.

 

Secondary Roads

* Route 802 (Zion Church Road) – Bridge widening and guardrail installation from Route 522 to Route 639. Road closed beginning Sept. 7. Estimated completion is mid October 2010.

* Route 1026 (Happy Creek Road) Front Royal area – Road improvement project from Sixth Street and Bradford Drive to near Route 606 (Shenandoah Shores Road). Temporary lane closures 7 a.m. to 5 p.m., Monday to Friday. Happy Creek Road closed from Polk Avenue to Sixth Street until November 30 to reconstruct the Sixth Street intersection. Motorists should follow detour signs for alternate route. Lewis Street will be closed from Cannon Street to Happy Creek Road. Lewis Street traffic should use Meadow Lane. The speed limit in this work zone will be reduced to 25 mph. Beginning Aug. 31, traffic will be diverted to a single-lane, stone road with flagger traffic control and a pilot vehicle during work hours. Traffic will be restored to two-way traffic during non-work hours. Motorists are advised to drive with caution through the work zone and be aware of changes in traffic patterns.

* (NEW) Various roads – Brush cutting and mowing.

 

Vegetation management may occur district wide on various routes.

 

Motorists are reminded to use extreme caution when traveling through work zones. Traffic alerts and traveler information can be obtained by dialing 511. In areas where 511 is unavailable, dial

1-866-MY511VA (866-695-1182). Traffic alerts and traveler information also are available at 511Virginia.org.

 

VDOT can be followed on Facebook, Flickr, Twitter and You Tube. RSS feeds are also available for statewide information. The VDOT webpage is located at www.VirginiaDOT.org.

 

Highway safety is everyone’s responsibility. Virginia’s highway safety partnership — the Virginia Department of Transportation, Virginia Department of Motor Vehicles and Virginia State Police — challenges you to help prevent highway fatalities. Buckle up. Avoid distractions. Share the road. Drive drug- and alcohol-free. Obey speed limits. For more information on the Highway Safety Challenge and things you can do to avoid becoming Virginia’s next traffic fatality, visit www.safeVAhighways.org.

 

(END)

 

 



Information in VDOT news releases was accurate at the time the release was published. For the most current information about projects or programs, please visit the project or program Web pages. You may find those by searching by keyword in the search Virginia DOT box above.

Page last modified: Oct. 17, 2012