RELEASE:

CONTACT:
IMMEDIATE

Sandy Myers 540-332-9201
Sandy.Myers@vdot.virginia.gov
540-292-2500 (cell)
Ken Slack 540-332-9264
Ken.Slack@vdot.virginia.gov
540-414-5670 (cell)
STA12-168

Nov. 30, 2012



TRAFFIC ALERT FOR WEEK OF DECEMBER 3-7, 2012
Highway work zones in the Staunton District

STAUNTON – The following is a list of highway work that might affect traffic in the Staunton transportation district during the coming weeks. The Staunton district is comprised of 11 counties, Alleghany, Bath, Rockbridge, Augusta, Highland, Rockingham, Shenandoah, Frederick, Page, Warren and Clarke. Work scheduled is subject to change due to inclement weather and material supplies. Motorists are advised to watch for slow-moving tractors during mowing operations. Also, when traveling through a work zone, be alert to periodic changes in traffic patterns and lane closures.

 

(NEW)   Indicates a new or revised entry since last week’s report.

 

ALLEGHANY COUNTY

Interstate 64

* (NEW) Bridge deck maintenance at Exit 10 over Dunlap Creek. Single lane closures, eastbound and westbound, 7 a.m. to 5 p.m., Monday to Friday. Estimated completion Dec. 7, weather permitting.

* Mile marker 0 to 41, eastbound and westbound – Debris removal and clean ditches. Monday to Friday, 8 a.m. to 5 p.m.

 

Primary Roads 

* (NEW) Route 42 over the C & O Railway – Flagger traffic control of single alternating lane closures for bridge inspection. Tuesday, Dec. 4, 8 a.m. to 4 p.m. 

* (NEW) Brush cutting at various primary locations, Monday to Friday, 8:30 a.m. to 4 p.m.

 

Secondary Roads

* Route 617 – Road closed for widening and safety improvements. Estimated completion is May 2013.   

* Route 633 – Replacement of Cowpasture River Bridge and approaches from 1.46 miles south of Route 634 to 1.14 miles south of Route 634. Be alert for flagger traffic control. Estimated completion is May 17, 2013.

* Route 638 (Natural Well Road) – Bridge over Jackson River closed until further notice for repairs. This location is 0.1-mile west from Route 687 (Jackson River Road) to 0.6-mile east from Route 666 (Morris Hill Road). Motorists can use the following routes for a detour:  Route 687 to Route 641 (Indian Draft Road) to Route 666.

* (UPDATE) Various roads – Shoulder repairs, pipe replacement, brush cutting and drainage repairs. Flagger traffic control, Monday to Friday, 8:30 a.m. to 4 p.m.

 

 

BATH COUNTY

Primary Roads

No lane closures reported.

 

Secondary Roads

* Various roads – Brush cutting, patching, and grading. Flagger traffic control, Monday to Friday, 8:30 a.m. to 4 p.m.

 

 

ROCKBRIDGE COUNTY

Interstate 64

* (UPDATE) Mile marker 57 to 41, eastbound and westbound – Tighten up guardrail cables, debris removal and ditch cleaning. Monday to Friday, 8 a.m. to 5 p.m.

 

Interstate 81

* (UPDATE) Mile marker 173 to 205.5, northbound and southbound – Tighten up guardrail, debris removal and ditch cleaning. Monday to Friday, 8 a.m. to 5 p.m.

* (UPDATE) Mile marker 195 to 199, northbound single lane closures – Truck climbing lane project. Dec 4, 5 and 6, 8 p.m. to 7 a.m.

 

Primary Roads

* Route 11 - Utility project at Route 763 (Lincoln Road). Install water transmission line on northwest shoulder of Route 763 for 0.60 mile to the intersection of Route 11. Installation will continue on the east should of Route 11 northbound for 1.23 miles. The crossover at Lincoln road may be closed as well as other crossovers as the work progresses. Work includes boring at the intersection of Route 763 and across all lanes of Route 11 to the west shoulder of the southbound lanes. Estimated completion is January 2013.  

* Route 251 – Utility tree trimming. Flagger traffic control during daylight hours, Monday to Friday.

 

Secondary Roads

 * Various roads – Grading, pot hole repairs, pipe replacement, ditching, and brush cutting. Flagger traffic control, Monday to Friday, 8:30 a.m. to 4 p.m.

* (NEW) Various roads – Utility tree trimming. Flagger traffic control during daylight hours, Monday to Friday.

 

 

HIGHLAND COUNTY

Primary Roads

* (NEW) Route 250 – Brush cutting at various locations on Bullpasture Mountain. Monday to Friday, 8:30 a.m. to 4 p.m.

 

Secondary Roads

* (NEW) Route 600 (Upper Backcreek Road) – Ditch cleaning at various locations. Flagger control, Monday to Friday, 8:30 a.m. to 4 pm.

* Various roads – Tree trimming, grading, and pothole repair. Flagger traffic control, Monday to Friday, 8:30 a.m. to 4 p.m.

 

 

AUGUSTA COUNTY 

Interstate 64

* (NEW) Mile marker 89.5 to 93.0, eastbound – Guardrail placement. Right shoulder closure, weekdays, 7 a.m. to 6 p.m.

* (UPDATE) Mile marker 97.1 to 106.4, eastbound and westbound – Afton Mountain Guardrail Project. Guardrail replacement and installation. Left lane closures and right shoulder closures, Monday to Friday, 8 a.m. to 10 p.m.

 

Interstate 81

* (UPDATE) Mile marker 195 to 237, northbound and southbound – Tighten up guard rail cables, debris removal and ditch cleaning. Monday to Friday, 8 a.m. to 5 p.m.

 

Primary Roads

* (UPDATE) Route 11 (Lee Highway, Greenville), northbound and southbound – Sewer construction. Shoulder closures, Monday to Friday, 7:30 a.m. to 4 p.m. Estimated completion is Dec. 31.

* Route 252 – Utility tree trimming. Flagger traffic control during daylight hours, Monday to Friday.

* (NEW) Routes 340 at Route 654 in Stuart Draft – Traffic Signal Replacement. Estimated completion March 2013.

* Route 340 – Waynesboro, Delphine Avenue Project. Sanitary line work and barrier wall placement from Delphine Avenue to 4th Street. Be alert for lane closures and flagger traffic control. Work is Monday to Friday, 7 a.m. to 5:30 p.m.

* Various roads – Mowing, pipe installation, patching, brush cutting, shoulder repairs, ditching and grading. Monday to Friday, 8 a.m. to 4:30 p.m.

 

Secondary Roads

* Route 891 (Newton Lane) Rural rustic road paving project, Monday to Friday, 7 a.m. to 3:30 p.m. Estimated completion is Dec. 5.

* Various roads – Mowing, pipe installation, patching, brush cutting, shoulder repairs, ditching and grading. Monday to Friday, 8 a.m. to 4:30 p.m.

* Various roads – Utility tree trimming. Flagger traffic control during daylight hours, Monday to Friday.

 

 

ROCKINGHAM COUNTY 

Interstate 81 

* (UPDATE) Mile marker 237.51 to 263.9, northbound and southbound – Debris removal, clean bridge slope, ditch cleaning and sign work. Monday to Friday, 8:30 a.m. to 4:30 p.m.

 

Primary Roads

* Route 11, northbound – Bridge work on the bridge over Cooks Creek just north of the intersection with Route 257 near Bridgewater. Beginning Sept. 24, lane closures with a traffic barrier will be in place 24 hours-a-day, seven days-a-week. Traffic reduced to a single 12-foot lane with a 14-foot clear width between the barrier. Estimated completion is late December.

* Route 33, westbound – Construction from Route 602 to Route 644. Shoulder and lane closures, weekdays, 8 a.m. to 5 p.m.

* Route 33, westbound (Rawley Pike) – Waterline installation at intersection of Route 726. Shoulder closed, weekdays, 7:30 a.m. to 4 p.m.

* (NEW) Route 42 – Utility tree trimming. Flagger traffic control during daylight hours, Monday to Friday.

* Route 211 – Paving, pavement marking and shoulder stone. Pilot vehicle and flaggers. Single lane closure, weekdays, 7 a.m. to 7 p.m.

* (UPDATE) Route 253 (Port Republic Road), eastbound and westbound – Pedestrian rail installation on Route 253 Bridge over I-81. Single lane closures, Monday night to Friday morning, 8 p.m. to 6 a.m.  Estimated completion Dec. 14, weather permitting.

* Route 253 (Port Republic Road) – Turn lane and commercial entrance permit work from Harrisonburg City limits to Route 726 (Stone Spring Road). Work zone will have shoulder closures and intermittent right-lane closures.

* Various roads – Spot leveling. Pilot vehicle and flaggers. Single lane closure, Weekdays, 7 a.m. to 7 p.m.

* Various roads – Mowing, pipe installation, patching, brush cutting, shoulder repairs, ditching and grading. Monday to Friday, 7 a.m. to 3:30 p.m.

 

Secondary Roads 

* Stone Spring Road – Erickson Avenue/Stone Spring Road Connector Project from Route 11 to Port Republic Road. Lane and shoulder closures, daily, 8 a.m. to 5 p.m. Estimated completion is spring 2013.

* Route 602 – Construction from Route 602 to Route 644. Shoulder closures with flagger traffic control, weekdays, 8 a.m. to 5 p.m.

* Route 609 (Naked Creek Road) – Naked Creek Bridge Project. Replacement work at the intersection of Route 603 (Fleeburg Road, Page County) and Route 609. Periodic temporary lane closures, daily, 8 a.m. to 5 p.m. On May 22, the traffic pattern will shift from the existing bridge on Route 603 to a temporary bridge during construction of the permanent structure. Estimated completion is April 2013.

* Route 726 (Erickson Avenue) – Waterline installation from Route 33 (Rawley Pike) to Harrisonburg City limits. Intermittent lane closures with flaggers controlling traffic, Monday to Friday, 8 a.m. to 5 p.m.

* Route 727 (Airport Road) – Bridge from Route 11 (Lee Highway) to Route 696 (Kisers Road). Road closed until further notice.

* Route 1421 (Springbrook Road, Town of Broadway) – Replacement of bridge over Linville Creek and signalization upgrade at Route 42. Possible single lane closures controlled by flaggers Monday to Friday, 7:00 a.m. to 5:30 p.m. Estimated completion is April 30, 2013.Work zone is from 0.275 miles west of Route 42 (South Main Street) to Route 42.

* Various roads – Pothole patching hard surface roads and machining dirt roads. Flagger traffic control, Monday to Friday, 8:30 a.m. to 4 p.m.

* Various roads – Mowing, pipe installation, patching, brush cutting, shoulder repairs, ditching and grading. Monday to Friday, 7 a.m. to 3:30 p.m.

* Various roads – Tree trimming. Flagger traffic control during daylight hours, Monday to Friday.

 

 

PAGE COUNTY

Primary Road

* Route 340 – Bridge construction work over Compton Creek and Norfolk Southern Railway and approaches, 1.40 miles south of the Page and Warren County lines to 3.50 miles south of the Page and Warren County lines. Daily lane closures with flagger traffic control. Shoulder closures, 24 hours-a-day. Motorists should use extreme caution and obey posted speed limit. Estimated completion is fall 2013. The bridges are still under construction but the portion of Route 340 from 3.27 miles to 2.95 miles south of the Page and Warren County line will open with new travel lanes after noon on Monday, Nov. 26. Motorists should use extra caution in this area as drives become familiar with this new traffic pattern.

* Various roads – Mowing, pipe installation, patching, brush cutting, shoulder repairs, ditching and grading. Monday to Friday, 7 a.m. to 3:30 p.m.

 

Secondary Roads

* Route 603 (Fleeburg Road) – Naked Creek Bridge Project. Replacement work at the intersection of Route 603 and Route 609 (Naked Creek Road). Periodic temporary lane closures, daily, 8 a.m. to 5 p.m. Estimated completion is April 2013.

* Route 686 (Smeltzer’s Road) – Compton Creek/Norfolk Southern Railroad Bridge project. New alignment of Route 340 (Stonewall Jackson Memorial Highway). Intersection of Route 686 (Smeltzer’s Road) and Route 340, from 0.24 miles south of the intersection of Route 662 (Compton Hollow Road) at Route 340, was permanently closed on May 23. A cul-de-sac will be constructed at the west end of Route 686. Motorists wishing to access Route 686 will need to turn off of Route 340 onto Route 662 and travel 0.26 miles east on Route 662 to the intersection of Route 686. Signs will be posted.

* Various roads – Mowing, pipe installation, patching, brush cutting, shoulder repairs, ditching operations and grading. Monday to Friday, 7 a.m. to 3:30 p.m.

 

 

SHENANDOAH COUNTY

Interstate 81

* (UPDATE) Mile marker 263.9 to 298, northbound and southbound – Debris removal, brush cutting and clean under bridge slopes. Monday to Friday, 8:30 a.m. to 4:30 p.m.

 

Primary Roads

* (NEW) Traffic Signal Replacement at Routes 11/55/1203 in Strasburg. Estimated completion is April 2013.

 

* (NEW) Traffic Signal Replacements – Route 11 at Route 1974 (Holiday Street) in Strasburg. Estimated completion is April 2013.

 

Secondary Roads

* (NEW) Route 604 (Scheffer Gap Road) closed for pipe replacement.25 miles west of Route 681 (Alonzaville Road). Monday Dec. 3 to Dec. 4, weather permitting.

* (NEW) Various roads – Scraping, brush cutting, mowing and drainage work. Monday to Friday.

* Various roads – Tree trimming, Monday to Friday. Flagger traffic control during daylight hours, Monday to Friday.

 

 

FREDERICK COUNTY

Interstate 81

* (UPDATE) Mile marker 300 to 324, northbound and southbound – Debris removal, sign work, brush cutting and cleaning drains and culverts. Monday to Friday, 8:30 a.m. to 4:30 p.m.

 

Primary Roads

* (NEW) Various roads - Mowing and shoulder work, Monday to Friday.

 

Secondary Roads

* (NEW) Various roads – Scraping, pipe cleaning, brush cutting and ditching, Monday to Friday.

* Various roads – Utility tree trimming. Flagger traffic control during daylight hours, Monday to Friday.

.

 

CLARKE COUNTY

Primary Roads

* (NEW) Route 7 – Single lane closure westbound over the Shenandoah River for bridge inspection (mile marker 16-17).  Dec. 6 and 7, 8 a.m. to 4 p.m.

* Route 7 Business (West Main Street) – Mosby Boulevard Project. Construction of Route 636/Mosby Boulevard extension. Work is Monday to Thursday, 7 a.m. to 5 p.m. Estimated completion is May 2013.

* (NEW) Various roads - Mowing, Monday to Friday.

 

Secondary Roads

* (NEW) Various roads – Shoulder work, Monday to Friday.

* Various roads – Utility tree trimming. Flagger traffic control during daylight hours, Monday to Friday.

 

 

WARREN COUNTY

Interstate 66

* (UPDATE) Mile marker 0 to 13, eastbound and westbound – Debris removal. Monday to Friday, 8:30 a.m. to 4:30 p.m.

* Mile marker 0 to 15, eastbound and westbound – Bridge deck maintenance. Possible single lane traffic, Monday to Thursday, 8 a.m. to 3 p.m.

 

Interstate 81

* (UPDATE) Mile marker 298 to 300, northbound and southbound – Debris removal, Monday to Friday, 8:30 a.m. to 4:30 p.m.

 

Primary Roads

No lane closures reported.

 

Secondary Roads

* Various roads – Utility tree trimming. Flagger traffic control during daylight hours, Monday to Friday.

 

 

Vegetation management may occur district wide on various routes.

 

Motorists are reminded to use extreme caution when traveling through work zones.

 

Traffic alerts and traveler information can be obtained by dialing 511. Traffic alerts and traveler information also are available at www.511Virginia.org. For other assistance call the VDOT Customer Service Center, available 24 hours-a-day, seven days a week. Citizens can dial 1-800-FOR- ROAD (1-800-367-7623) from anywhere in the state to report road hazards, ask transportation questions, or get information related to Virginia’s roads.

 

VDOT can be followed on Facebook, Flickr, Twitter and YouTube. RSS feeds are also available for statewide information. The VDOT Web page is located at www.VirginiaDOT.org.

 

(END)



Information in VDOT news releases was accurate at the time the release was published. For the most current information about projects or programs, please visit the project or program Web pages. You may find those by searching by keyword in the search Virginia DOT box above.

Page last modified: Nov. 30, 2012