I-64 Battlefield Boulevard Project
Schedule
As a result of weather conditions or other factors, this schedule is subject to change.
Fall 2006/Winter 2007 (Nov. 2006- Feb. 2007)
- Completed construction of the new eastbound extension at I-464.
- Completed the transition of the existing interchange to a temporary configuration with traffic lights to enable demolition and construction of the first phase of the Battlefield Boulevard bridge.
Spring/Summer 2007 (Mar. 2007- Aug 2007)
- Opened the first phase of the new Battlefield Boulevard bridge.
- Began demolition of the existing bridge to enable construction of the new interstate lanes.
Fall 2007/Winter 2008 (Sep. 2007- Feb. 2008)
- Completed I-64 mainline traffic shifts to the collector/distributor lanes (CD lanes).
- Began demolition of the old interstate lanes.
Spring/Summer 2008 (Mar. 2008-Aug. 2008)
- Begin construction of the new interstate concrete travel lanes and HOV lanes.
Fall 2008/Winter 2009 (Sep. 2008-Feb. 2009)
- Complete the new Battlefield Boulevard interchange.
- Remove the temporary lights on Battlefield Boulevard.
- Complete I-64 mainline construction and place traffic in its final configuration.
Spring/Summer 2009 (Mar. 2009-Jul. 2009)
- Final project completion.
- Remove temporary widenings.
- Complete all services such as Traffic Management Systems, lighting, and overhead message boards.