460 Connector - Phase II |
Project at a Glance
Project Updates
Phase II
VDOT is currently evaluating an unsolicited proposal to construct a rough grade road bed for the Route 460 Phase II, approximately 6.2-miles in length.
The Federal Highway Administration (FHWA) has approved the environmental assessment for the project and VDOT has obtained the independent mineral specialist review for the project.
- January 2010 – VDOT received Finding of No Significant Impact from FHWA (FONSI)
A public hearing for the location of Route 460 Connector Phase II was held Tuesday, July 14, 2009 from 4-7 p.m. at Breaks Interstate Park. Approximately 140 citizens were in attendance.
- November 2009 – CTB approved Location of Route 460 Connector Phase II