Map of construction project districts

Recently Completed

Interstate 81 bridges over Route 808 (Halls Bottom Road) near Exit 10

Project at a Glance

Begin Date
September 2016

Est Completion Date
September 2018

Cost
$11.3 million

Contractor
Orders Construction Company, St. Albans, W. Va.

Locality
Washington

District
Bristol

Contact
Craig Jones, P.E., Area Construction Engineer
(276) 228-2154

What's Happening Now?

Replacement of the Interstate 81 bridges over Halls Bottom Road near Exit 10 in Washington County finished September 2018.

Project Overview

In Summer 2016, Orders Construction Company, St. Albans, W.Va., was awarded the contract to design and construct the I-81 bridges over Route 808 (Halls Bottom Road) in Washington County, located near exit 10. The project is valued at $11.3 million.

Construction began in September 2016 and finished September 2018, on time and on budget.

 

 

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: Sept. 19, 2018