In Design

Route 53 and Route 618, Fluvanna County

Construction of roundabout

Project at a Glance

Begin Date
Fall 2019

Est Completion Date
Winter 2020

Phase
In Design

Cost
$3.67 million

Lengths and Limits
Intersection of Rt. 53 and Rt. 618

Locality
Fluvanna

District
Culpeper

Contact
John Rose
540-829-7429
Stacy Londrey
540-727-3201

Attend a Public Hearing

VDOT invites residents and other interested parties to attend a design public hearing on Tuesday, June 13, 2017 from 4:30 to 6:30 p.m. at the Fluvanna County Public Library, 214 Commons Boulevard, Palmyra, VA 22963. 

The public hearing is an opportunity to give VDOT comments and/or suggestions regarding the proposed project. Representatives from VDOT will be available to answer questions and take public comments.

Written comments may also be sent to John Rose, Project Manager, VDOT Culpeper District, 1601 Orange Road, Culpeper, VA 22701, or John.Rose1@vdot.virginia.gov. A comment worksheet is linked below.

Project Purpose

The purpose of the project is to construct a roundabout at the existing "T" intersection of Route 53 (Thomas Jefferson Parkway) and Route 618 (Lake Monticello Road).

VDOT originally proposed to construct a left-turn lane at this intersection to reduce the number of rear-end and left-turn collisions. However, in 2015, Fluvanna County applied for $2.9 million in additional funding through SMART SCALE to construct a roundabout at this intersection. The project was ranked as one of the top five projects in the commonwealth for safety and was subsequently funded by the Commonwealth Transportation Board in June 2016.

Approximately 7,700 vehicles use Route 53 daily, according to 2016 data. The traffic count on Route 618 is 3,100 vehicles per day. 

Project Details

The project will replace the existing intersection with a single lane roundabout to improve traffic safety and more effeciently move traffic through the intersection. The roundabout will include enhanced street lighting and pedestrian accommodations.

A 5-foot sidewalk along the northeast quadrant of the intersection and along the south side of Route 618 will accommodate pedestrians. A marked crosswalk across Route 618 will connect the existing JAUNT bus stop in the parking lot of the Effort Baptist Church with future Park and Ride spaces that are planned to be included in the proposed development to the north of the intersection.

Construction is anticipated to take about one year and will require periodic lane closures. The public will be notified about traffic impacts and changes through media reports, social media posts and 511.

Project Schedule

Public hearing: June 13, 2017
Public comment period ends: June 23, 2017
Construction start: Fall 2019
Construction completion: Winter 2020

Project schedule is subject to change.

Project Costs

Total Cost: $3.67 million

Engineering of Roadway Plans: $824,062
Right of Way Acquisition, Relocation Assistance and Utility Relocation: $750,000
Construction: $2,100,000

Cost is subject to change as the design is developed.

Resources and Information

Public hearing materials: June 13, 2017

Project overview video

SMART SCALE application

SMART SCALE scorecard Adobe Acrobat PDF (165 KB)

Share Your Input on Rt. 53-618 Roundabout Project
News release, June 2, 2017

UPC 96938

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: June 12, 2017