Proposed
Route 614 (Twymans Mill Road), Madison County |
| Improvements to intersection with Route 706 (Turner Drive) |
Project at a Glance
Scheduled for June 2014 advertisement
Cost
$931,253 estimated
Lengths and Limits
0.13 mile; from 0.01 mile west to 0.12 mile east of Route 706 (Turner Drive)
Locality
Madison
District
Culpeper
Contact
Howard Tomlinson
540-829-7436
Project Purpose
The primary purpose of this project is to improve sight distance at the intersection of Route 614 (Twymans Mill Road) and Route 706 (Turner Drive) in Madison County.
What Is Proposed?
Work will include re-grading Route 614 and modifying its side slopes with a goal of improving safety at the intersection.
The existing roadway is approximately 18 feet wide with variable shoulder widths. The road’s current condition impacts the available sight distance at the intersection.
VDOT will close Route 614 for a 10-week period during construction. The proposed detour route uses Route 15 (James Madison Highway) to Route 622 (Tanners Road) to Route 705 (Twymans Mill Road) and back to Route 614.
According to a 2010 traffic count, Route 614 carries 430 vehicles per day at this location. Route 706 carries 150 vehicles per day.
Project Costs
Total Cost: $931,253
Engineering of Roadway Plans: $400,000
Right of Way Acquisition and Utility Relocation: $114,335
Construction: $416,918
These costs are preliminary planning estimates and subject to change as the project is finalized.
Project Schedule
Public hearing: September 25, 2012, 5-7 p.m.
Madison County Administration Building
County Auditorium
414 N. Main Street
Madison, VA 22727
Public comment period ends: October 5, 2012
Right of way acquisition and utility relocation: July 2013
Construction advertisement: June 2014
Resources and Project Information
News release: VDOT to Hold Hearing on Rt. 614 Improvements
Public hearing brochure
(122 KB)