In Design
Route 15/29 and Route 229, Culpeper |
| Widening and intersection improvements, town of Culpeper |
Project at a Glance
Scheduled 2013
Cost
$7.6 million (2011-2016 Six-Year Improvement Program estimate)
Lengths and Limits
0.25 mile; Route 15/29 Business to Fairview Avenue
Locality
Culpeper
District
Culpeper
Contact
Brian Arnold
540-829-7557
Project Purpose
The primary purpose of this project is to improve the intersection of Route 15/29 Business and Route 229 in the town of Culpeper. Approximately 28,000 vehicles per day use this intersection.
What is Proposed?
The improvements include a two-lane roundabout that will replace the current signalized intersection. A sidewalk will be built on the west side of Route 15/29 and a 10-foot-wide shared use path will be built on the east side of Route 229 and the north side of Route 15/29. The intersection will also accommodate the future construction of the planned Inner Loop road.
Route 229 north of the intersection to Fairview Avenue will be expanded to four lanes from the current two lanes. The intersection approaches on Route 15/29 Business will also be reconstructed to tie into the roundabout.
As part of the design of this project, a traffic analysis was done to compare the function of a roundabout with a signalized intersection. This study concluded that a roundabout will provide more efficient traffic movements and a safer intersection.
Project Schedule
Design Public Hearing: June 29, 2010
Public Comment Ends: July 9, 2010
Design Approval: Winter 2010
Right of Way Acquisition and Utility Relocation Begins: Winter 2010
Construction Begins: Spring 2013
Project Costs
The latest estimated project costs from the 2011-2016 Six-Year Improvement Program:
Total Cost: $7,600,000
Design and Engineering: $600,000
Right of Way Acquisition and Utility Relocation: $2,000,000
Construction: $5,000,000
These costs are preliminary planning estimates and subject to change as the project develops. Estimates will be updated as the project progresses. This project will be financed using federal funds.