Map of construction project districts

Under Construction

Fall Hill Avenue Widening and I-95 Bridge Replacement

City of Fredericksburg

Project Photos

Project at a Glance

Begin Date
Construction begins February 2015

Est Completion Date
January 2017

Phase
Construction

Cost
Estimated cost $44.4 million

Contractor
Design-Build Team: Whitman, Requardt & Associates and Corman Construction

Locality
Fredericksburg

District
Fredericksburg

Contact
Michael Coffey, VDOT Area Construction Engineer
(540) 899-4288
Kelly Hannon, VDOT Communications Manager
(540) 374-3344

About the Project

The Virginia Department of Transportation is widening Fall Hill Avenue from the two existing lanes to four lanes with a raised median from Carl D. Silver Parkway (Central Park) to a roundabout just west of the bridge over the Rappahannock Canal.

Mary Washington Boulevard will be extended to intersect with the roundabout, which will provide a new connection between Route 1 (Jefferson Davis Highway) and Fall Hill Avenue.

In addition, the existing bridge over Interstate 95 will be widened from two lanes with no shoulders or sidewalks to four lanes with pedestrian facilities on both sides. 

Fall Hill Avenue carries approximately 17,200 vehicles per day, and the number of vehicles is expected to double in the next 20 years.

Fall Hill Avenue will remain open to traffic during the project, with periodic lane closures during off-peak hours. 

Project Fact Sheet

Construction Updates

Summer 2015

Construction is now underway on the entire project. Construction on the Interstate 95 overpass has been underway since February 2015. 

Motorists will observe tree and brush clearing along Fall Hill Avenue and the future extension of Mary Washington Boulevard. For motorist safety, this work will require intermittent traffic stops and single-lane closures on Fall Hill Avenue from 9 a.m. to 4 p.m. on Monday-Friday during the weeks of June 22-26, June 29-July 2, and July 6-10. Motorists should follow the direction of flagging crews in the work zone.

Construction continues to build the relocated entrance to Heritage Park Apartments. The new entrance will provide improved sight distance for motorists and align with Bragg Hill Drive. The new entrance is expected to open to traffic the week of June 29-July 2. 

Utility relocation work is underway throughout the project.

Bridge construction continues on the first half of the new 4-lane overpass across I-95. Crews have driven piles to stabilize the soil, and have built bridge piers and pier caps. Next, crews will focus on lifting bridge beams into place. This work will require brief overnight traffic stops on I-95. Specific dates will be announced and advertised in advance to alert travelers.

Project Documents

“Pardon Our Dust” Meeting  

VDOT held a "Pardon Our Dust" public meeting from 5-7 p.m. on December 2, 2014 at James Monroe High School to share information about the upcoming construction project. 

Meeting Brochure

Meeting Presentation

Map 1

Map 2

Construction Sequence and Phases

Project Milestones 

Advance Utility Construction and I-95 Bridge Construction

Utility relocation in some areas of the project corridor began in fall 2014, and will continue through winter 2015.

Bridge construction will begin in February 2015.

Fall Hill Widening/Mary Washington Boulevard Extension 

Construction to widen Fall Hill Avenue and extend Mary Washington Boulevard will begin in spring 2015. 

Project Completion

January 2017

 

 

 

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: June 19, 2015