Map of construction project districts

Coming Soon

Route 3 Business (Chatham Bridge) Bridge Superstructure Replacement

Project at a Glance
Begin Date
Project advertisement January-March 2020, with bridge closure and detour estimated to begin summer 2020

Est Completion Date
Early 2022

Phase
Preliminary engineering

Cost
$22 million

Contractor
To be determined

Locality
Fredericksburg and Stafford

District
Fredericksburg

Contact
Byrd Holloway, VDOT Project Manager
(540) 899-4288
Kelly Hannon, VDOT Communications Manager
(540) 374-3344

About the Project

Preliminary engineering work is underway for a project to replace the superstructure of the Chatham Bridge, which is located on Route 3 Business and connects Stafford County and the City of Fredericksburg.

The bridge spans the Rappahannock River. The current bridge was built in 1941 and carries 16,000 vehicles a day. 

The four-lane bridge requires significant maintenance and a new superstructure to improve its condition. The project will remove the bridge's current posted weight limit, which is 21 tons for single unit vehicles and 26 tons for tractor-trailers. 

This $22.2 million project will be funded by the State of Good Repair program, which funds improvements to deficient bridges and pavements across Virginia. 

The bridge will be closed to all traffic for approximately 16 months during construction. Signs posted along the detour route of Blue and Gray Parkway and Dixon Street will guide residents and visitors between downtown Fredericksburg and Stafford County.

Before the bridge is closed to traffic, improvements to the Dixon Street exit ramp will be completed. The ramp will be widened to create a longer right turn lane with more space to hold vehicles turning right at the ramp signal. 

Detour Route Map

New Project Schedule: March 2019 Update

The Virginia Department of Transportation is advancing the Chatham Bridge Rehabilitation Project to start construction sooner than originally scheduled.

Advertisement of the bridge rehabilitation project to potential bidders has been accelerated from its original date of October 2020 to early 2020, between January and March of 2020. 

Construction is now anticipated to begin in the later half of 2020, and the bridge will be closed to traffic over 16 months over a range from late 2020 to early 2022.   

This means the improved bridge and pedestrian path will open to motorists, walkers, bicyclists and runners nearly a year sooner, in early 2022 instead of late 2022. 

Work has been advanced due to more rapid deterioration of the bridge deck, which includes the travel surface. Even with pothole patching on a regular basis by VDOT crews, motorists are experiencing a rough ride crossing the bridge, especially in the eastbound right travel lane. 

VDOT crews will continue to perform routine spot maintenance to Chatham Bridge until construction begins.

The Chatham Bridge is safe for travel. The bridge received a full inspection in fall 2018. The bridge will continue to be inspected leading up to the beginning of the project. If there was any concern regarding the safety of the bridge, or an individual travel lane of the bridge, it would be closed to traffic immediately.

New Project Schedule: Fact Sheet

DESIGN PUBLIC HEARING: January 25, 2018

A design public hearing was held on January 25, 2018, to share information and proposed designs on the Chatham Bridge Rehabilitation Project and to invite public comment on the proposed design.

Meeting Brochure

Meeting Comment Sheet

Meeting Handout: Dixon Street Detour Route

Meeting Display 1

Meeting Display 2

Meeting Display 3

Rehabilitation of Chatham Bridge Video

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: March 27, 2019