Map of construction project districts

Coming Soon

I-564 Intermodal Connector

Norfolk

Project at a Glance

Begin Date
Spring 2013

Cost
$169 Million

Contractor
TBD

Locality
Norfolk

District
Hampton Roads

Contact

Customer Service
800-367-7623

Project Information

The purpose of this project is to provide a safe, high-speed, highway connection from the existing I-564 to the Norfolk International Terminals and the Norfolk Naval Station. This road realignment will alleviate congestion and improve the level of service on city and naval station streets. The road repositioning will also reduce truck traffic on the adjacent roadways, in addition to being the first section in place for the proposed next project, Patriot's Crossing. 

Overall Goals of the Project

  • Reduce traffic demand through the underpass at the airfield
  • Give direct interstate access to the port authority at the working piers
  • Allow for the future Patriot's Crossing project to be accessible via I-564

Key Elements of the Project

  • Four lanes separated by a grass median
  • A realignment of I-564 for future crossings under the Elizabeth River
  • The redirection of truck traffic from Hampton Boulevard to the ports
  • Installation of variable message signs and traffic cameras

Navy Triangle Improvements

  • Fleet Recreational Park was a replacement recreational facility for the Norfolk Naval Base that allowed VDOT to use the previous site for the widening of Hampton Boulevard and the construction of the I-564 Intermodal Connector.
  • Hampton Boulevard will create a grade separation thus eliminating the need to interrupt vehicular traffic for railway movement in to and out of the port terminals.
  • The Intermodal Connector will realign I-564 to Hampton Boulevard with improved access into Naval Station Norfolk and Norfolk International Terminals.
  • Patriot's Crossing will create a connection from I-564 to I-664 which will travel under the Elizabeth River.

 

Current Status

The Navy and VDOT agreed to the basic layouts of the Intermodal Connector and the Air Terminal interchange in September. VDOT and the Navy entered into a new Memorandum of Agreement (MOA) in December 2012, to replace the previous agreement that had expired. Currently, VDOT, FHWA-EFL and the Navy are drafting an MOA that allows FHWA to manage the bidding and construction phases of the project. The tri-party team is also working to procure a design-build team and to obligate construction funds by summer 2013.

Project Schedule

• Award Design-Build Contract – August 2013
• Issues Notice to Proceed – September 2013
• Final Design Approval – Spring 2014
• Complete Construction – June 2016

Public Meeting Items

A public meeting in December 2012.At this meeting, the public was provided information regarding the project’s scope, purpose and need. Representatives from VDOT, the U.S. Navy, the city of Norfolk and FHWA were available to discuss specific issues and answer questions about the project.

Project Land Display

Project Land Display 2

Project Brochure

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: May 6, 2013