I-64 High Rise Bridge Waterproof and Repair Deck

Chesapeake

Project at a Glance

Begin Date
July 25, 2016

Est Completion Date
January 2018

Cost
$3.7 million

Lengths and Limits
I-64 westbound lanes (towards VaBeach)

Contractor
Corman Construction

Locality
Chesapeake

District
Hampton Roads

Contact
Hampton Roads Public Affairs
757-925-1647

Project Details

 The Virginia Department of Transportation (VDOT) will begin the I-64 West High Rise Bridge waterproofing and deck repair project on Monday, July 25. Motorists can expect weeknight single-lane closures as early as 8 p.m. to 5 a.m. the following morning, heading from Chesapeake to Virginia Beach.

Crews will first patch the existing concrete bridge deck, then place an epoxy overlay on the westbound lanes of the I-64 High Rise Bridge. The epoxy-based material prevents excessive water from seeping into the roadway, which through expansion and contraction during hot and cold temperatures, can cause potholes or pooling. Additional repairs to the steel superstructure are also a part of this project.

Crews will be working for the rest of this year as temperatures allow. The project’s contract completion date is January 2018. Similar work was completed on the eastbound lanes in 2012. 


 