James River Bridge Grid Deck Replacement |
| Isle of Wight County (Route 17) |
Project at a Glance
Winter 2013
Cost
$3.8 million
Contractor
Curtis Contracting
Locality
Isle of Wight
District
Hampton Roads
Contact
Hampton Roads Public Affairs
757-925-1660
About Project
This project removed the existing steel grid deck, performed various repairs to the deck substructure, installed a new steel grid deck, and balanced the counterweights of the lift mechanism.
Crews completed both the north and south bound grid deck spans on Dec 17, 2012. The project was ahead of schedule and on budget.