Project at a Glance

Begin Date
October 2012

Est Completion Date
August 2013

Cost
$1.5 million

Contact

About the Project

This project will redesign the intersection of Oak Grove Road and Green Tree Road in the City of Chesapeake. The project is approximately 1500 ft. long with a roundabout style intersection replacing the original triangular intersection. Updates will also be made to the storm drain, water and sewer utilities, curb and gutter, in addition to concrete and asphalt paving.

City of Chesapeake Project Page

Current Status

The project was completed in August 2013.

Project Schedule

March 2013 Complete municipal water and sewer utility relocations 

April 2013 Storm drain pipe and structures will near completion

June 2013 Work will begin on grading and paving Roundabout 

July 2013 Crews will perform traffic switches

August 2013 Open to Traffic