Route 58 Plant Mix Mill and Overlay

Suffolk

Project at a Glance

Est Completion Date
Summer 2012

Cost
$3 million

Contractor
Branscome

Locality
Suffolk

Contact
Paul Moose
757-925-1663

Project Information

Crews repaved both the east and west bound lanes on Route 58 from the I-664/I-64 Interchange in Chesapeake to the Suffolk city line; a total of 3.5 miles.  Work began in August 2011.


Current Status: The project was completed on time and within budget on June 12, 2012.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 