Recently Completed: Route 301 Over Nottoway River Bridge Replacement

Cost and schedule ►


Traffic alerts ►

A project to demolish and replace the Route 301 bridge over the Nottoway River.

Construction began in September 2016 under a $2.7 million contract with English Construction. The project was originally scheduled for completion on Dec. 21, 2017.

Benefits 

The new bridge is 265 feet long and 32 feet wide. The bridge approach road is rebuilt.

Major Milestones 

The Route 301 bridge over the Nottoway River opened to traffic Oct. 24, 2017 nearly two months ahead of schedule.