Schedule

Schedule

NOTE: Project schedule is subject to change based on weather and other circumstances. The Virginia Department of Transportation will update this schedule as needed.

March 16, 2006

April 2006

July 12, 2006

Early 2007

  • First phase of sound wall construction begins between I-295 North towards I-64 West and the Twin Hickory neighborhoods of Cobblestone Landing and Parsons Walk COMPLETED
  • Complete the sound wall behind the Reflections at West Creek  COMPLETED

March 2007

Spring/Summer 2007

  • I-295 South traffic shift from current southbound lanes to shared use of northbound lanes between I-64/I-295 interchange and Nuckols Road COMPLETED
  • Ramp from I-64 West to I-295 South shifted to new location heading towards Nuckols Road COMPLETED
  • Overnight detour (10:00 p.m.-5:30 a.m.) of I-64 East onto Broad Street, in order to place structural steel over I-64 East for the new flyover bridge COMPLETED

Summer 2007

Summer/fall 2007

  • Demolition of existing Pouncey Tract Road bridge to require overnight detours (10:00 p.m.-5:30 a.m.) of I-64 east and west to Route 250 (Broad Street) COMPLETED

  • Overnight detour (10:00 p.m.-5:30 a.m.) of I-64 West onto Broad Street, in order to place structural steel over I-64 west for the new flyover bridge. COMPLETED

Fall/winter 2007

  • Complete the first phase of the sound wall between I-295 North towards I-64 West behind Parsons Walk and Cobblestone Landing. COMPLETED
  • Overnight detour (10:30 p.m.-5:30 a.m.) of I-64 onto Broad Street, in order to place structural steel for the new southbound section of the Pouncey Tract Road bridge COMPLETED

June 2008

September 15, 2008

December 31, 2008

      January 12, 2009

      Through January 2009

      • Opening additional lane I-64 East and West between Route 288 and the I-295 interchange. COMPLETED

      Early 2009

      • Second phase of sound wall construction begins between I-295 North towards I-64 and the Twin Hickory neighborhoods of Waters Edge and Cobblestone Landing. COMPLETED 

      Spring 2009

      • Overnight detour (10:30 p.m.-5:30 a.m.) of I-64 onto Broad Street in order to demolish the existing I-295 South bridge. COMPLETED 

      • Complete the second phase of the sound wall between I-295 North towards I-64 West behind the neighborhoods of Cobblestone Landing and Waters Edge. COMPLETED

      • PROJECT COMPLETE (May 28, 2009)