Schedule
NOTE: Project schedule is subject to change based on weather and other circumstances. The Virginia Department of Transportation will update this schedule as needed.March 16, 2006
- News release: Commonwealth Transportation Board Awards Contract to English Construction Co. Inc. for $49 Million
April 2006
- Phase
I construction begins
- News release, April 11, 2006: I-295/I-64Construction
to Begin in Western Henrico
- Public Information Meeting, Deep Run High School Held April 19,
2006
- Sound wall construction along I-64 east, west of Pouncey Tract Road, behind the Reflections at West Creek apartments COMPLETED
July 12, 2006
Early 2007
- First phase of sound wall construction begins between I-295 North towards
I-64 West and the Twin Hickory neighborhoods of Cobblestone Landing and Parsons
Walk COMPLETED
- Complete the sound wall behind the Reflections at West Creek COMPLETED
March 2007
- News release, March 30, 2007: Speed Limit
Decreased on Pouncy Tract Road As Part of the I-295 Flyover Project
- News release, March 12, 2007: I-64 Traffic
to be Detoured Two Nights for I-295 Flyover Project (updated)
- News release March 5, 2007: I-64 Traffic to be Detoured Two Nights for I-295 Flyover Project
Spring/Summer 2007
- I-295 South traffic shift from current southbound lanes to shared use of
northbound lanes between I-64/I-295 interchange and Nuckols Road
COMPLETED
- Ramp from I-64 West to I-295 South shifted to new location heading towards
Nuckols Road COMPLETED
- Overnight detour (10:00 p.m.-5:30 a.m.) of I-64 East onto Broad Street, in order to place structural steel over I-64 East for the new flyover bridge COMPLETED
Summer 2007
- Traffic shifts to new Pouncey Tract Road bridge, maintaining two lanes of
travel. Work begins on demolition of existing structure after Verizon
relocation. COMPLETED
- News release Sept. 18, 2007: Beam placements for I-295 flyover bridge start tomorrow night
Summer/fall 2007
- Demolition of existing Pouncey Tract Road bridge to require overnight
detours (10:00 p.m.-5:30 a.m.) of I-64 east and west to Route 250 (Broad
Street) COMPLETED
- Westbound
detour
- Eastbound detour
Fall/winter 2007
- Complete the first phase of the sound wall between I-295 North towards I-64
West behind Parsons Walk and Cobblestone Landing. COMPLETED
- Overnight detour (10:30 p.m.-5:30 a.m.) of I-64 onto Broad Street, in order
to place structural steel for the new southbound section of the Pouncey Tract
Road bridge COMPLETED
June 2008
- Pouncey Tract Road bridge widened to four lanes of travel. COMPLETED
- News release June 12, 2008: Pouncey Tract Road Bridge Widening Complete
September 15, 2008
- Traffic Advisory: I-64 west traffic pattern changes
December 31, 2008
January 12, 2009
- New flyover bridge complete. Motorists on I-64 East traveling to I-295 South will use the new flyover bridge. COMPLETED
- News release: I-295 Flyover Ramp to Open Tonight--I-64 east drivers should expect a new traffic pattern
Through January 2009
- Opening additional lane I-64 East and West between Route 288 and the I-295 interchange. COMPLETED
Early 2009
- Second phase of sound wall construction begins between I-295 North towards I-64 and the Twin Hickory neighborhoods of Waters Edge and Cobblestone Landing. COMPLETED
Spring 2009
- Overnight detour (10:30 p.m.-5:30 a.m.) of I-64 onto Broad Street in order
to demolish the existing I-295 South bridge. COMPLETED
- News release: I-295 Flyover Project Complete