Schedule
NOTE: Project schedule is subject to change based on weather and other
circumstances. The Virginia Department of Transportation will update this
schedule as needed.
March 16, 2006
April 2006
July 12, 2006
Early 2007
- First phase of sound wall construction begins between I-295 North towards
I-64 West and the Twin Hickory neighborhoods of Cobblestone Landing and Parsons
Walk First phase completed
- Complete the sound wall behind the Reflections at West Creek
COMPLETED
March, 2007
Spring/Summer 2007
- I-295 South traffic shift from current southbound lanes to shared use of
northbound lanes between I-64/I-295 interchange and Nuckols Road
COMPLETED
- Ramp from I-64 West to I-295 South shifted to new location heading towards
Nuckols Road COMPLETED
- Overnight detour (10:00 p.m.-5:30 a.m.) of I-64 East onto Broad Street, in
order to place structural steel over I-64 East for the new flyover bridge
COMPLETED
Summer 2007
Summer/fall 2007
- Demolition of existing Pouncey Tract Road bridge to require overnight
detours (10:00 p.m.-5:30 a.m.) of I-64 east and west to Route 250 (Broad
Street) COMPLETED
Overnight detour (10:00 p.m.-5:30 a.m.) of I-64 West onto Broad Street, in
order to place structural steel over I-64 west for the new flyover
bridge. COMPLETED
Fall/winter 2007
- Complete the first phase of the sound wall between I-295 North towards I-64
West behind Parsons Walk and Cobblestone Landing. COMPLETED
- Overnight detour (10:30 p.m.-5:30 a.m.) of I-64 onto Broad Street, in order
to place structural steel for the new southbound section of the Pouncey Tract
Road bridge COMPLETED
June 2008
Through spring 2009:
- Opening additional lane I-64 East and West between Route 288 and the I-295
interchange. Sections will be opened to traffic as they are completed.
Fall 2008
- New flyover bridge complete. Motorists on I-64 East traveling to I-295 South
will use the new flyover bridge.
Early 2009
- Second phase of sound wall construction begins between I-295 North towards
I-64 and the Twin Hickory neighborhoods of Waters Edge and Cobblestone Landing
Spring 2009
- Overnight detour (10:30 p.m.-5:30 a.m.) of I-64 onto Broad Street in order
to demolish the existing I-295 South bridge
- Complete the second phase of the sound wall between I-295 North towards I-64
West behind the neighborhoods of Cobblestone Landing and Waters Edge
Page last modified: Thursday, July 03, 2008