March 15 Virtual Public Information Meeting Info

Please note: A virtual public information meeting will be held Monday, March 15 (in case an alternate date is needed, the meeting will be held Monday, March 22) from 7 p.m. to 8:30 p.m. 

This project's improvements at the intersection of Fox Mill Road (Route 665) and Pinecrest Road include:

  • Installing a traffic signal
  • Constructing left-turn lanes on northbound and southbound Fox Mill Road 

At the intersection, Fox Mill Road averages 13,000 vehicles a day and Pinecrest Road averages up to 2,500.

Estimated Costs
Preliminary Engineering - $850,000
Right of Way Acquisition and Utility Relocation - $1.5 million
Construction - $3.3 million
Total - $5.7 million

This project is financed with Fairfax County funding.

Benefits 

This project aims to relieve congestion and improve safety and operations at the intersection.

Major Milestones 

Virtual Public Involvement - May - June 2020
Begin Preliminary Engineering - December 2020
Virtual Public Information Meeting - March 15, 2021
Virtual Public Information Meeting Comment Deadline - March 25, 2021
Begin Right of Way Acquisition - Summer 2023
Begin Construction - Fall 2024

Resources

Contact Info:

Christopher Barksdale, P.E.
Location & Design
703-259-2768

Andrew Beacher, P.E.
Preliminary Engineering
703-259-2239

Other relevant links:

Virtual Public Involvement Presentation - May 2020

Previous Meetings >>

Major funding source: Fairfax County

Phase: In Design

UPC: 118460

State ID: 0665-029-428, P101, R201, C501

Lat/Long: 38.933159, -77.378294

Locality: Fairfax

Page last modified: Feb. 25, 2021