Map of construction project districts

Recently Completed

1-95 Bridge Over Route 619

VDOT replaced the two north and southbound I-95 bridges over Route 619 in Prince William County

Area Map

Project Photos

Project at a Glance

Begin Date
June, 2000

Est Completion Date
November 30, 2001

Cost
$6.7 million

Contractor
Abernathy Construction Corp., Glen Allen, VA

Locality
Prince William

District
Northern Virginia

Contact
Prince William Construction

Project Updates

VDOT replaced the two 36-year-old north and southbound I-95 bridges over Route 619 in Prince William County. The new bridges have wider shoulders and two additional lanes for future HOV use.

Contacts

Prince William Construction
Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects

Page last modified: May 5, 2004