Map of construction project districts

Under Construction

Braddock Road and Pleasant Valley Road

Roundabout in western Fairfax County

Area Maps

Click to view full-size map>

Project Photos

Project at a Glance

Begin Date
June 2015

Est Completion Date
Spring 2016

Approx. $5.8 million total

Fort Myer Construction Corporation


Northern Virginia

Chan Basnayake, P.E.
Design-Build Project Manager
Oscar Jamilla, PMP
Sr. Construction Manager
Shirlene Cleveland, P.E.
Program Manager for Design-Build Projects

A "Pardon Our Dust" Meeting for the Braddock Road/Pleasant Valley roundabout project was held April 14, 2015. View the presentation here.

Construction Update

Construction work started June 2015. Traffic control signs and perimeter controls have been installed. Installation of drainage structures are ongoing as well as utility relocation work. Four variable message boards are onsite and activated as necessary.

About the Project

This design/build project will construct a roundabout at the intersection of Braddock Road (Route 620) and Pleasant Valley Road (Route 609) in Fairfax County.

As of 2012, about 7500 vehicles per day travelled this section of Braddock Road and about 8500 travelled along Pleasant Valley Road.

The roundabout will provide additional capacity for forecasted traffic volumes and improve safety by eliminating the potential for turn/angle crashes at the intersection. It will also enhance pedestrian access for residents in the area.

The new roundabout includes crosswalks and curb ramps for pedestrians, landscaping and lighting. The sidewalk will be tied into the existing trail along the east side of Pleasant Valley Road south of the intersection.


The intersection is currently a four-way stop, with a single lane in each direction. 

During weekday peak hours, the intersection experiences substantial congestion, operating at full capacity with extensive backups on Braddock Road eastbound in the mornings and westbound in the evenings. The congestion results in severe delays, causing the intersection to operate at a service level of “F” (failing) during peak periods.

Designs for improvements here must take into account parkland, commercial property, an Agricultural-Forestal District, wetlands, rare habitats, and significant overhead utility poles. Taking these constraints into consideration, VDOT, in cooperation with Fairfax County, prepared preliminary plans.

Traffic Impacts

There will be no lane closures during rush hours. Drivers can expect occasional lane closures with flagging on weekdays 9:30 a.m. to 3 p.m. (Fridays removed by 2 p.m.) and nighttime lane on closures weekdays and during weekends, as needed.


Notice to Proceed (NTP) Letter (July 2014)
Award Letter (June 2014)
Notice of Intent to Award (May 2014)
Traffic Operations Analysis (Jan. 2013)
Design Public Hearing Brochure and Exhibit (Oct. 2013)
Section 4(f); De Minimis Concurrence FCPA (Oct. 2013)
Final Traffic Alternatives
Traffic Data Boards
Categorical Exclusion (CE)
Documentation of FHWA Review
Waters of the U.S. Boundary Delineation Report
DCR Conservation Areas with Conceptual Baseline Overlay
USACE Preliminary Jurisdictional Determination
Waters of the U.S. Boundary Delineation Map with Conceptual Baseline Overlay

Study: Planned Roundabout Will Not Increase Delays at Nearby Intersections (Jan. 2014)
Comment Period Extended for Public Hearing (Oct. 2013)


UPC: 103318  State Project: 0620-029-017,P101  Federal Project: STP-5A01(382)

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: July 28, 2015