Proposed
Delaney Road Bridge Repairs |
| Substructure replacement over Neabsco Creek in Prince William County |
Project Photos
Project at a Glance
Spring 2012
Locality
Prince William
District
Northern Virginia
Contact
Fawaz Saraf
703-586-7684
Ray Burkhardt
703-259-2967
About the Project
This project would replace the entire existing timber deck and steel beam substructure of the Delaney Road (Route 2025) bridge over Neabsco Creek in Prince William County.
The single-span bridge is about 25 feet long, with one lane in each direction. It is currently rated as structurally deficient and is posted with a limit of 22 tons (single-axle truck) and 33 tons (semi truck) due to deterioration of the existing timber deck and thirteen steel support beams. To avoid closing the bridge, emergency temporary repairs to add support brackets and strengthen the steel beams were completed in 2009.
The new bridge surface will be slightly wider, within the available room of the existing abutments. The entire superstructure will be replaced with solid pre-cast, pre-stressed concrete slabs.
Construction is tentatively scheduled to begin in spring 2012. All work will be performed within existing right-of-way.
Traffic Impacts
Construction will require complete closure of the bridge for approximately six weeks. Signs will be installed along the four-mile detour route. Click below for an enlarged view of the detour route.

Resources
Project Plans
Environmental Document (Programmatic Categorical Exclusion)
Project #2025-076-039


























