Fairfax County Parkway and Terminal Road

Intersection/safety improvements in Fairfax County
Project Photos
Project at a Glance
Begin Date
April 2017

Est Completion Date
Construction Completed: November 2017

Final Completion:
January 2018

Cost
$2.3 million

Lengths and Limits
Just north of Terminal Rd to just north of Backlick Rd

Contractor
Sagres Construction

Locality
Fairfax

District
Northern Virginia

Contact
Yusaf Masud, P.E.
Construction
703-259-2973

About the Project

This project made safety improvements at the intersection of the Fairfax County Parkway (Route 286) and Terminal Road. It also added a third southbound lane with merge area on Fairfax County Parkway from Terminal Road to the next traffic signal at Backlick Road.

Improvements to the Fairfax County Parkway/Terminal Road intersection included:

  • Converting the existing southbound Fairfax County Parkway right-turn lane to a right-turn/through lane 
  • Adding a second left-turn lane on northbound Fairfax County Parkway
  • Widening the crossover
  • Reconstructing the traffic signal

Estimated Costs
Preliminary engineering: $558,000
Construction: $1.7 million
Total: $2.3 million

Resources

Notice of Willingness (June 2016)
Programmatic Categorical Exclusion 

Project Numbers
UPC: 105501
State: 0286-029-163, P101, RW201, C501
Federal: HSIP-5A01 (666)