Gallows Road over Route 50, Phase 2

Bridge rehabilitation in Fairfax County

Area Maps

Project Photos

Project at a Glance

Begin Date
Phase 1 - Sept. 2015

Phase 2 - March 2017

Est Completion Date
Phase 1 - July 2016

Phase 2 - June 2018

Cost
Phase 1 - $430,000

Phase 2 - $4.3 million

Contractor
Phase 2 -
Martins Construction

Locality
Fairfax

District
Northern Virginia

Contact
Thomas Mulcahy, P.E., CCM
Construction
(Phase 2)
703-259-3350
Vincent Brumfield
Structure & Bridge
(Phase 1)
703-366-1967

Note: This project was completed in June 2018.

About the Project

This project rehabilitated the Gallows Road (Route 650) bridge over Route 50 (Arlington Boulevard). The bridge was built in 1985. 

This was the second phase of the project. Phase 1 (pier repairs) was completed in July 2016. 

The 2015 average daily traffic was 39,000 vehicles for Gallows Road and 41,000 for Route 50 under the bridge.

Schedule
Phase 1 Begin Construction - September 2015
Phase 1 Completion - July 2016
Phase 2 Begin Construction - March 2017
Phase 2 Completion - June 2018

Resources

Public Information Meeting Presentation (June 2015)

Project Numbers
State: 0650-029-235 (Phase 1), 0650-029-239 (Phase 2)
UPC: 106956 (Phase 1), 106949 (Phase 2)