Place holder
Travel Center
Place holder
News
Place holder
Info Center
Place holder
Business Center
Place holder
Programs
Place holder
Projects
Place holder
About
Place holder
Jobs
Place holder
Sitemap
Place holder
Call 1-800-FOR-ROAD



Map of construction project districts

Under Construction

Glebe Road over Route 50

Bridge replacement and widening in Arlington

Project Photos

Project at a Glance

Begin Date
April 21, 2011

Est Completion Date
October 14, 2012

Cost
$6.5 million

Contractor
Ft. Myer Construction Corporation

Locality
Arlington

District
Northern Virginia

Contact

Charles Mel Harvey
Area Construction Engineer
703-259-3234

Jay Babra
Construction Manager
703-259-2944

About the Project

This $6 million project ($958,000 preliminary engineering, $4.9 million construction) replaces and widens the Glebe Road bridge over Arlington Boulevard (Route 50). The entire bridge deck, about 100 feet long, will be replaced with pre-cast, pre-stressed concrete panels. The new span will be about 27 feet wider than the current bridge.

Renderings of the new bridge (below) show some of the following features planned:

  • a northbound left-turn lane to Route 50
  • a 17-foot shared use path on one side, 11-foot sidewalk on the other
  • improved site distance for right turns from Route 50 to Glebe Road
  • new signals
  • decorative wrought-iron picket fencing, gateway pillars and LED lighting


Renderings of the new Glebe Road bridge and lane configuration.
 

Traffic Impacts

Drivers can expect traffic shifts and lane closures in the project area. Daytime closures in both directions on Route 50 will begin at 9 a.m. Closures on westbound Route 50 will re-open by 2 p.m. to minimize impacts to rush hour traffic. Drivers can also expect lane closures on Glebe Road from 9 a.m. until 3 p.m.

No additional detours are anticipated at this time.

Project Updates

  • Abutment A: Crew is working on footing, wing wall A and extension of the abutment.
  • Abutment B: Crew is working on the footing, wing wall C and stem walls.
  • Backfill for the abutments is ongoing. The crew is scheduled to start work on wing walls B and D.
  • Contractor is on schedule.

Resources

Community Meeting Presentation (June 2, 2011)


Project Number: 0120-000-118, C501, B609 (UPC 18860)

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: April 12, 2012

 


Connect With Us...
View VDOT photo galleries on Flickr Find VDOT on Facebook  Subscribe to the VDOT RSS feed (Home Page)  Follow VDOT on Twitter   Visit the VDOT YouTube Channel