Map of construction project districts

In Design

Hunter Mill Road over Difficult Run

Constructing a permanent bridge in Fairfax County

Project Photos

Project at a Glance

Begin Date
Summer 2018

$2.2 million


Northern Virginia

Brian Morrison, P.E.
Structure & Bridge

About the Project

The purpose of this project is to replace the temporary Hunter Mill Road (Route 674) bridge over Difficult Run.  A temporary bridge was installed in November 2011 to replace the original structurally deficient bridge while VDOT developed plans for a permanent structure.   

The bridge width will be widened to accommodate an 11-foot wide lane in each direction and four-foot wide shoulders to address recommendations by the 2006 Hunter Mill Road Traffic Calming Study.  Accelerated construction will take place along with reusing the temporary bridge foundations to minimize the construction duration.  The bridge length will be approximately 50 feet.  Hunter Mill Road at Difficult Run will be closed for approximately 20 days during construction and traffic will be detoured as it was during installation of the temporary bridge.

The existing bridge has an average traffic count of 17,000 vehicles per day, and a projected count of 22,000 vehicles per day for the design year of 2035.

Schedule & Costs

Anticipated Schedule
Advertisement - January 2018
Construction – Summer 2018 

Estimated Costs

Preliminary engineering: $390,000
Right-of-way and utilities: $435,000
Construction: $1.4 million
Total: $2.2 million


Design Public Hearing displays | brochure (June 2015)
Community meeting presentation (December 2014)

Project Numbers

State: 0674-029-989
UPC: 102691

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: July 15, 2016