Lee Highway and Nutley Street

Intersection improvements in Fairfax County

Project Photos

Project at a Glance

Begin Date
June 2013

Est Completion Date
December 20, 2013

Cost
Estimated $1.5 million

Contractor
Arthur Construction Co.

Locality
Fairfax

District
Northern Virginia

Contact
Charles M. Harvey
Area Construction Engineer
703-259-3234
Larry Lethcoe
Construction Manager
703-259-1763
Emanuel Reta
571-991-4300

Note: This project was completed on December 20, 2013.

About the Project

This project made several improvements to the intersection of Lee Highway (Route 29) and Nutley Street (Route 243) in Fairfax County, including:

  • Adding a second left-turn lane from eastbound Lee Highway to northbound Nutley Street
  • Constructing a raised concrete median along Route 29 just east of Nutley to improve safety
  • Upgrading the existing traffic signal equipment

 

Estimated Project Cost

Preliminary engineering: $315,000
Right of way: $200,000
Construction: $1 million
Total: $1.5 million
 

State Project: 0029-029-S56,P101,R201,M501  Fed. STP-5A01(211)  UPC: 100648