Map of construction project districts

Under Construction

Route 606/Loudoun County Parkway/Old Ox Road

Reconstruction and Widening

Area Maps

Click to view full-size map>

Project Photos

Project at a Glance

Begin Date
September 2015

Est Completion Date
Fall 2017

Cost
$107.7 million

Lengths and Limits
Evergreen Mills Road to the Dulles Greenway

Locality
Loudoun

District
Northern Virginia

Contact
Sanjeev Suri, P.E., PMP
Project Manager
703-259-2232
Jeff Austin (Shirley Contracting, LLC)
Project Manager
703-668-0288 ext. 25
C. Michael Pruitt
Construction Manager
571-659-1981
Shirlene Cleveland, P.E.
Program Manager for Design Build Projects
703-691-6710

Traffic Alert

On Friday, Feb. 5 between the morning rush and afternoon rush, patching will occur on potholes that formed due to the recent severe winter weather. There will be mobile lane closures for very brief periods with minimal impact on traffic. 

Pothole patching will resume Monday, Feb. 8 if needed and as weather permits.  

Construction Update

In January, work continued on the foundations for the bridge over the Horsepen Lake spillway. Clearing has also been occurring throughout the project area. 

In February, scheduled work includes rock blasting and the installation of storm drainage.

About the Project

Loudoun County Parkway/Old Ox Road (Route 606) connects two major roads, Route 50 and Route 28 (Sully Road) and is a desirable route for motorists from points west to access Ashburn, Sterling and Herndon. The road is currently congested in both directions during peak hours. This project will address the need to increase capacity on this section of road due to growth in the surrounding area and the resulting increase in traffic congestion.

The project will:

  • Reconstruct and widen the existing two-lane rural road to four lanes between Evergreen Mills Road (Route 621) and the Dulles Greenway (Route 267) (a distance of about 5 miles) 
  • Include provisions for bicyclists and pedestrians.

Schedule

VDOT awarded the design-build contract to the Shirley/Dewberry team on May 14, 2014 for approximately $77 million.  The NTP (Notice to Proceed) was issued on June 19, 2014.  Survey and final design were the first items to occur following the NTP, with construction having begun in September 2015.  Final completion is scheduled in the fall of 2017.

Project Background

Planning for the widening of the Route 606 corridor between Route 50 and the Dulles Greenway has been ongoing since the early 1990s. The first segment was implemented in 2002-03 with the reconstruction and widening between Route 50 and Evergreen Mills Road.  

The project will implement the ‘Interim Condition’ as described in Loudoun County’s Countywide Transportation Plan. This plan calls for Route 606 to be a controlled-access, median-divided urban collector. The ultimate condition as described in the Countywide Transportation Plan calls for a limited-access, median-divided urban arterial. The proposed design implements the interim condition while enabling a future conversion to its ultimate condition.

The Metropolitan Washington Airport Authority (MWAA), Loudoun County and Virginia Department of Transportation (VDOT) are jointly funding the project, which is being developed by VDOT.

Resources

PDFs

"Pardon Our Dust" meeting presentation (June 2015)

Noise Abatement Guidelines and Noise Abatement Design Study Reports

Summary Report of Design Public Hearing (15 MB)

Public hearing brochure and exhibits (21 MB) (June 2013)

Environmental assessment (9 MB)

Federal Highway Administration FONSI and FONSI Rationale

Typical section

 

UPCs: 97529 (State Project Number: 0606-053-983,P101), 105064, 105575

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: Feb. 4, 2016