Poland Road and Edgewater Street

Constructing a permanent roundabout in Loudoun County

Project Photos

Project at a Glance

Begin Date
February 2018

Est Completion Date
Fall 2018

$1.6 million

Arthur Construction


Northern Virginia

Raymond Kollack

Michael Gleasman, P.E.

About the Project

This project is replacing the temporary marked and delineated roundabout at the intersection of Poland Road and Edgewater Street with a permanent single lane roundabout, to include a raised center island, raised splitter islands, and curb/gutter along the approaches to improve safety at the intersection.

Schedule & Costs


First Willingness Notice - June 2016
Second Willingness Notice - November 2016
Advertise for Construction – November 2017
Award Construction Contract - January 2018
Begin Construction - February 2018
"Pardon Our Dust" Meeting - March 14, 2018
Estimated Completion - Fall 2018

Estimated Costs

Preliminary Engineering: $470,000
Right of Way: $80,000
Construction: $1.1 million
Total: $1.6 million

Traffic Impacts

Drivers can expect daytime flagging at the intersection during the following times:

  • Monday through Thursday: 9 a.m. to 3:30 p.m.
  • Friday: 9 a.m. to 2 p.m.


Second Notice of Willingness  (November 2016)

First Notice of Willingness (June 2016)

Aerial of intersection

Programmatic Categorical Exclusion

Project Numbers

State: 0742-053-127, P101, R201, M501
UPC: 106942