Map of construction project districts

In Design

Richmond Highway Corridor Improvements

Widening Route 1 and multimodal improvements from Jeff Todd Way to Napper Road in Fairfax County

Area Maps

Project at a Glance

Begin Date
Construction: 2023

Phase
In Design

Cost
$215 million

Lengths and Limits
Jeff Todd Way to
Napper Road

Locality
Fairfax

District
Northern Virginia

Contact
William Dunn, P.E.
Project Manager
703-259-2950
Anissa Brown, P.E.
Environmental
703-259-3358

New! The interactive map is now live.

Richmond Highway interactive map

About the Project

VDOT is working to improve safety, reduce congestion, and help increase the community’s multimodal options along almost three miles of Route 1 from Jeff Todd Way to Napper Road. This project will:

• Widen Richmond Highway from four to six lanes
• Add separate bicycle lanes and sidewalks on both sides of the road
• Reserve median width to accommodate Fairfax County's future dedicated bus-only lanes

All pedestrian and bicycle facilities will be ADA-compliant, turn lanes will be extended wherever possible to improve safety and capacity, and signals throughout the corridor will also be optimized.

For more information visit Fairfax County's site on the county's Bus Rapid Transit (BRT) project and the Embark Richmond Highway initiative. While BRT will not be constructed as part of this project, VDOT and Fairfax County are closely coordinating as both projects move forward.
Design, field survey activities, environmental field work and studies are underway, along with traffic data collection and analysis.

The project team continues public outreach and meetings as design progresses. To schedule a local visit to your community, use the contacts on this page.

Background

In 2015, the Route 1 Multimodal Alternatives Analysis, sponsored by VDOT, the Department of Rail and Public Transportation, the Office of Intermodal Planning and Investment, as well as Fairfax and Prince William counties, identified improvements needed to best meet the needs of both the community and corridor travelers. Key recommendations included a Bus Rapid Transit system constructed in three phases; long-term, a three-mile extension of the Metro Yellow Line to Hybla Valley, and short-term, widening Route 1 with bicycle and pedestrian facilities.  

Estimated Schedule & Cost

Public Information Meetings - April and November 2017, April 2018
Design Public Hearing - Fall 2018
Approve Design - Winter 2018/19
Begin Right of Way Acquisition - Spring 2019 
Begin Utility Relocation - Summer 2020
Begin Construction -  Spring 2023

Preliminary Engineering: $12.5 million
Right of Way & Utility Relocation: $142 million 
Construction: $60 million 
Total: $215 million

The project is currently funded through preliminary engineering with Regional Surface Transportation Program, revenue-sharing and Northern Virginia Transportation Authority funds. 

Resources

Public Information Meetings

April 4, 2018 (Ad)

Interactive Map
Meeting Materials: English | Spanish | Korean
Display Boards: Preferred Design Alternatives | Traffic Analysis | Bird's Eye View


November 6, 2017 (Ad)

Brochure: English | Korean | Spanish and Presentation
Meeting Displays: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18

April 18, 2017
(Ad)

Brochure: English | Spanish | Korean and Presentation 
Meeting Displays: Sacramento Drive and Cooper Road | Highland Lane and Frye Road | South County Government Center | Buckman Road and Mt. Vernon Highway | Access Management Principles | Traditional and Superstreet intersection options | Crash History | Purpose and Need | Typical Sections for Route 1 and Stormwater Management


State: 0001-029-205, P101, R201, C501
UPC: 107187

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: May 7, 2018