In Design: Rolling Road Widening and Old Keene Mill Road Intersection Improvements in Fairfax County
Cost and schedule ►
Public outreach ►
Old Keene Mill Road Intersection Improvements
Plans include:
- Adding a second left turn lane from Rolling Road (Route 638) to westbound Old Keene Mill Road (Route 644)
- Adding a dedicated right turn lane to eastbound Old Keene Mill Road
- Upgrading the traffic signal
- Improving the intersection alignment
Rolling Road Widening
Plans include:
- Widening Rolling Road from two to four lanes between Viola Street and Old Keene Mill Road
- Traffic signal upgrades
- A shared-use path for bicyclists and pedestrians
- Access management improvements
The project team has worked with Fairfax County to consider alternative design options, including the possibility of undergrounding utilities. This option was evaluated based on feasibility, potential property impacts, cost and schedule. This is no longer being pursued due to cost.
Estimated Costs
Preliminary Engineering: $7.2 million
Right of Way Acquisition and Utility Relocation: $23.3 million
Construction: $48.4 million
Total: $78.9 million
This project is financed with federal, state, county and Northern Virginia Transportation Authority funds.
Benefits
This project aims to relieve congestion, improve safety for drivers, bicyclists and pedestrians and improve operations.
Major Milestones
Public Information Meeting - June 2016
Public Information Meeting - November 2017
Categorical Exclusion Reevaluation Document Available - February 2018
Design Public Hearing - February 2018
Begin Old Keene Mill Road Intersection Right of Way Acquisition - July 2019
Begin Rolling Road Widening Right of Way Acquisition - February 2020
Advertise Old Keene Mill Road Intersection for Construction - October 2020
Award Old Keene Mill Road Intersection Construction Contract - December 2020
Begin Old Keene Mill Road Intersection Construction - Early 2021
Begin Rolling Road Widening Construction - Early 2024
Resources
Christopher Barksdale, P.E.
Location and Design
703-259-2768
Andrew Beacher, P.E.
Preliminary Engineering
703-259-2239
Other relevant links:
Preliminary Traffic Management Plans for Rolling Road Widening - August 2019
General Notes, Rolling Road Median Removal and Temporary Pavement Installation from Hunter Village Drive to Kenwood Avenue, Widening of Southbound Rolling Road from Birmingham Lane to Hunter Village Drive and Northbound Rolling Road from Glover Court to Kenwood Avenue, Widening of Northbound Rolling Road from Hunter Village Drive to Glover Court and Southbound Rolling Road from Kenwood Avenue to Birmingham Lane, Rolling Road Median Construction from Hunter Village Drive to Kenwood Avenue and Pedestrian Access
Noise Study - June 2019
Final Report and Appendices: A - C, D and E - J
Crosswalk Analysis Report - August 2018
Categorical Exclusion Reevaluation - February 2018 (Ad)
Major funding source: Federal and State
Phase: In Design
UPC: 5559, 109814
State ID: 0638-029-156, P104, R204, C504; 0638-029-337, R201, C501
Federal ID: STP-5401 (691), STP-5B01 (073)
Lat/Long: 38.771279, -77.231865
Locality:
Fairfax