Begin Date
Ground breaking took place on Oct. 22, 2007.

Est Completion Date
November 7, 2008

Locality
Fairfax

District
Northern Virginia

Contact
Mahmud M. Hussain, Resident Administrator,
703-383-2730

What's Being Done

Installation of a pedestrian bridge and fence on Route 50/Arlington Boulevard from 0.045 miles east of the Route 7 Overpass to 0.012 miles west of Patrick Henry Drive. The project length is .457 miles.

Design Approval

Public Hearing Displays

Benefits

This bridge will provide a safe route for pedestrians walking between two shopping areas.

Project Updates

The Pedestrian Bridge has completed 92 % of the required construction items.  Both the North and South ramps have been completed.  The steel truss is being re-fabricated due to cracks found in the original truss that was delivered in July 2008.  The black vinyl fence has been installed along east & west bound Route 50. The project is currently in suspension while waiting for the steel truss (to be delivered in early Spring 2009).

Contacts

Mahmud M. Hussain, Resident Administrator,, 703-383-2730
Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects