Map of construction project districts

Recently Completed

Route 50 Traffic Calming, Aldie

New landscaping, sidewalks and raised crosswalks

Project Photos


Project at a Glance

Begin Date
Fall 2011

Cost
$7.2 million total

Locality
Loudoun

District
Northern Virginia

Contact
Larry Tomlinson, P.E.
Area Construction Engineer
703-259-2304
Bill Atkins
Construction Manager
703-259-2939

What's Being Done

Traffic-calming in Aldie broke ground in fall 2011 and was completed in December 2012. The project is very similar to the Upperville project finished in 2008. Drivers approaching Aldie are now transitioned to the town speed limit with landscaping, sidewalks, and raised crosswalks and intersections in the village area.

The materials used for the sidewalks, curbs, crosswalks, and raised intersections were chosen to complement the historic and rural nature of the community.

Project cost:
$2.2 million - preliminary engineering
$200,000 - right of way
$4.8 million - construction

Return to the Route 50 Traffic Calming Page.

 

 

 