
Under Construction
Route 7 Turn Lane at Williams Gap Road |
West of Round Hill in Loudoun County |
Area Maps
Project at a Glance
December 2017
Est Completion Date
Summer 2018
Cost
$1.6 million
Lengths and Limits
Just east of intersection of Rt. 7 and Williams Gap Rd to intersection
Contractor
Tavares Concrete
Locality
Loudoun
District
Northern Virginia
Contact
Richard Gutridge
Construction
540-219-8944
Michael Gleasman, P.E.
Construction
703-259-1944
About the Project
The purpose of this project is to improve traffic operations and safety at the intersection of Route 7 and Williams Gap Road.
Westbound Route 7 is being widened with the addition of a 350 ft. long right-turn only lane plus a 200 ft. long taper. About 150 ft. of Williams Gap Road is being re-graded and hard-surfaced in order to effectively tie into the new turn lane. Drainage improvements are also being made within the project limits.
Schedule
Design Public Hearing - April 2016
Design Approval – August 2016
Right of Way Acquisition/Utility Relocation - Completed June 2017
Advertise for Construction - September 2017
Construction Contract Award - November 2017
Begin Construction – December 2017
Estimated construction completion - Summer 2018
Estimated Costs
Engineering of roadway plans - $460,000
Right of way acquisition and utility relocation - $276,000
Construction - $864,000
Total - $1.6 million
Traffic Impacts
Drivers can expect intermittent daytime single-lane closures during off-peak hours.
At least one lane of traffic will be open at all times.
Resources
Design Public Hearing (April 2016)
Project Numbers
State: 0007-053-107 P101, R201, M501
UPC: 106484
Federal: STP-053-9(025)