Map of construction project districts

Under Construction

Route 7 Widening - Rolling Holly Drive to Reston Avenue

From four to six lanes in Fairfax County

Area Maps

Click to view full-size map>

Project Photos

Project at a Glance

Begin Date
May 2013

Est Completion Date
December 2015

Cost
Approx. $37 million

Contractor
Fort Myer Construction Corporation

Locality
Fairfax

District
Northern Virginia

Contact
Michael Gleasman, P.E.
Area Construction Engineer
703-259-1944
Tim Diliscia
Construction Manager
540-247-9953
Kevin Dellinger
Sr. Project Inspector
571-722-9600

Field Office
46859 Harry Byrd Highway Suite 301 Sterling, VA 20164
(Open during normal business hours)
571-375-0174

About the Project

This section of Route 7 (Leesburg Pike) is severely congested in both directions during the morning and evening rush. Widening from and upgrading intersections will help relieve congestion and improve air quality, road operation and safety. In 2011, Route 7 carried 60,000 vehicles per day in this area and by 2034, is expected to carry 87,000 vehicles per day.

The project widens Route 7 from four to six lanes with a raised median and includes:

  • A 10-foot-wide shared-use path in both directions
  • Lengthened turn lanes
  • A new traffic signal at the intersection of Redberry Court and the relocated Woody’s Golf Course entrance
  • Improved intersection operation, particularly at Georgetown Pike, Route 7 and Seneca Road

Major utilities are located along this section of Route 7, including a 24-inch gas line, a 12-inch water line, fiber optic communications, telephone lines, and electrical lines. Utility relocation will continue through fall 2013 while the project is also under construction.

Project Update

Utility owners are continuing to move their utilities and will be completed by June.

The Contractor is currently working on retaining walls along the eastbound lanes of Route 7. The Contractor is placing barrier along the median and is currently working on Phase 1A in the median which includes construction of a temporary retaining wall, excavation and grading for placement of temporary asphalt in preparation for the next phase of work.

Two lanes of traffic will remain in each direction.

Traffic Impacts

Drivers can expect single-lane closures along Route 7 weekdays from 9:30 a.m. to 3 p.m. (noon Friday). Nighttime lane closures may also be in place 10 p.m. to 5 a.m. Sunday-Thursday nights, 10 p.m. Fridays to 9 a.m. Saturdays and 10 p.m. Saturdays to 8 a.m. Sundays. 

Resources

PDFs

Pardon our dust meeting presentation (June 2013)
Project plans and temporary access diagram (4 MB)

UPC: 52327
State Project: 0007-029-128, P101, R201, C501
 

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: April 3, 2014