Route 50 Traffic Calming, Middleburg

Traffic calming, pedestrian and safety improvements in the Town of Middleburg

Project Photos

Project at a Glance

Begin Date
October 2015

Est Completion Date
Fall 2016

$4.1 million

A&M Concrete Corporation


Northern Virginia

Scott Burdick
Michael Gleasman, P.E.

About the Project

This project will implement traffic calming, pedestrian and safety improvements along Route 50 (Washington Street) in the Town of Middleburg. The project will include new pedestrian lighting.  Also, the project has replaced and upgraded over 2,000 feet of water main.

Updates and information on the project are also posted on the Town of Middleburg website and the Town of Middleburg's Facebook page.

Traffic Impacts

Traffic on Route 50 is now back in its pre-project configuration, with the signal at Madison Street back in service.  The major elements of the project have been completed.  

There will be periodic flagging as needed for remaining work related to the sidewalks, lighting, landscaping and milling/paving.

Schedule & Costs

Begin construction - October 2015
Estimated completion - Fall 2016

Estimated Costs

Preliminary engineering: $697,000
Right of way: $38,000
Construction: $3.4 million
Total: $4.1 million


"Pardon Our Dust" meeting displays (October 2015): 1 2 3 4 5 6 7
Middleburg Streetscape Plan Concept: 1 2

Project Numbers

State: 0050-259-241,P101, R201, M501
UPC: 103887