Route 50 Traffic Calming, Middleburg

Traffic calming, pedestrian and safety improvements in the Town of Middleburg

Project Photos

Project at a Glance

Begin Date
October 2015

Est Completion Date
Late October 2016

Cost
$4.1 million

Contractor
A&M Concrete Corporation

Locality
Loudoun

District
Northern Virginia

Contact
Scott Burdick
Construction Manager
571-238-6246
Michael Gleasman, P.E.
Area Construction Engineer
703-259-1944

Traffic Alert

Starting the night of May 19, direct access from Madison and Pendleton streets to Route 50 (Washington Street) will be closed for approximately eight weeks.

Motorists on Madison Street and Pendleton Street will be able to access Route 50 by following detour signage.

Access to businesses in the affected areas will be maintained.

About the Project

This project will implement traffic calming, pedestrian and safety improvements along Route 50 (Washington Street) in the Town of Middleburg. The project will include new pedestrian lighting.  Also, the project will replace and upgrade over 2,000 feet of water main.

Updates and information on the project will also be posted on the Town of Middleburg website, as well as the Town of Middleburg's Facebook page.

Schedule & Costs

Schedule
Begin construction - October 2015
Estimated completion - Late October 2016

Estimated Costs

Preliminary engineering: $697,000
Right of way: $38,000
Construction: $3.4 million
Total: $4.1 million

Resources

"Pardon Our Dust" meeting displays (October 2015): 1 2 3 4 5 6 7
Middleburg Streetscape Plan Concept: 1 2

Project Numbers

State: 0050-259-241,P101, R201, M501
UPC: 103887