Route 29 Northbound Spot Widening

Adding a third northbound lane in the area of Pickwick Road in Fairfax County

Area Maps

Project Photos

Project at a Glance

Begin Date
May 2018

Est Completion Date
Winter 2018/19

Cost
$1.6 million

Lengths and Limits
Just south of Pickwick Rd to quarter-mile north of Pickwick Rd

Contractor
Arthur Construction

Locality
Fairfax

Contact
Demelew Teshome, P.E., PMP
Construction
571-238-4656
Chan Basnayake, P.E., PMP, CCM
Construction
703-259-2947

About the Project

This project is adding a third lane to northbound Route 29 from just before Pickwick Road to about a quarter-mile beyond the traffic signal.

The additional lane will create added capacity and will make northbound Route 29 three lanes the entire way between I-66 in Centreville and Union Mill Road. The entire section of southbound Route 29 between Union Mill Road and I-66 in Centreville is already three lanes.

The work also includes:

  • Paving and restriping
  • Traffic signal adjustments
  • Grading and drainage

Northbound Route 29 averages about 33,000 vehicles a day.

Schedule
Begin Preliminary Engineering - July 2017
Design Public Hearing - September 2017
Advertise for Construction - February 2018
Construction Contract Awarded - April 2018
Begin Construction - May 2018
Estimated Construction Completion - Winter 2018/19

Estimated Costs
Preliminary Engineering: $400,000
Construction: $1.2 million
Total: $1.6 million

Traffic Impacts

All lanes will be open at all times except during paving and restriping work. Drivers are asked to use caution when driving through the work zone.

Resources

Design Public Hearing (September 2017) 

Project Numbers
State: 0029-029-351,P101, R201, M501
UPC: 110330