Map of construction project districts

Under Construction

Sycolin Road Overpass

Over the Route 7/15 Bypass in Leesburg

Project Photos

Project at a Glance

Begin Date
June 2013

Est Completion Date
Opened to traffic August 12, 2014; entire project set for completion in October 2014

Cost
$17 million total

Contractor
Shirley Contracting Co., LLC

Locality
Loudoun

District
Northern Virginia

Contact
Jitender "Jay" Babra
Construction Manager
703-259-2944
Sanjeev Suri, P.E.
Design Build Manager
703-259-2232
Shirlene Cleveland, P.E.
Program Manager for Design Build Projects
703-691-6710

The overpass opened to traffic on August 12, 2014. View the press release.

About the Project

This project improves safety and traffic flow by replacing the existing signalized intersection with an overpass carrying Sycolin Road over the Route 7/15 Bypass.

The project eliminated the traffic signal and existing turn lanes from the Route 7/15 Bypass to Sycolin Road, and from Sycolin Road to the Bypass, removing direct access between the two roads. As a result, drivers on Sycolin Road now primarily use the Dulles Greenway or Battlefield Parkway to access the Bypass.

The new bridge over the Bypass includes two 12-foot travel lanes in each direction, a sidewalk along the southbound lanes, and a barrier-separated, shared-use path along the northbound lanes. 

The project also includes earth embankments and retaining walls, drainage improvements and guardrail.

Resources

PDFs
Public hearing project display and brochure (May 2012)
Typical sections
Environmental information: Cultural resources, historical resources, noise impacts and environmental document (Categorical Exclusion)

State Project Number: 6007-053-S96,P101,R201,C501,B666  UPC: 99256
Federal Project Number: STP-5A01(229)

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects