Coming Soon: The Woods Road Improvements, Phase 2 in Loudoun County

Cost and schedule ►

Public outreach ►

The second phase of this project will add turn lanes at the intersection of The Woods Road and Evergreen Mills Road. 

The first phase included realigning the road from just east of Understory Way to Evergreen Mills Road and paving the gravel portion. The new road features two ten-foot-wide travel lanes, as well as five-foot-wide paved shoulders for cyclists. 

Estimated Costs - Phase 1
Preliminary Engineering - $1.5 million
Right of Way Acquisition and Utility Relocation - $132,000
Construction - $3.9 million
Total: $5.5 million

Phase 1 was financed with state and county funding.

Estimated Costs - Phase 2
Right of Way Acquisition and Utility Relocation - $597,000
Construction - $1.9 million
Total - $2.5 million

Phase 2 is being financed with federal, state and county funding.

Benefits 

The project aims to improve safety and operations, as well as accommodate future expansion of the Loudoun County Landfill.

Major Milestones 

Location and Design Public Hearing - October 2013
Phase 1 Construction Start - 
April 2016
Phase 1 Open to Traffic/Substantially Completed - November 2016
Phase 1 Final Completion - April 2017
Phase 2 Begin Right of Way Acquisition/Utility Relocation - July 2017
Phase 2 Advertise for Construction - March 2019
Phase 2 Award Construction Contract - May 2019
Phase 2 Begin Construction - Summer 2019

Resources

Contact Info:

Calvin Britt, P.E.
Location & Design
(Phase 2)

Kimberly McCool, P.E.
Preliminary Engineering
(Phase 2)

Michael Gleasman, P.E.
Construction
(Phase 1)

Project Photos

Other relevant links:

"De minimis" Public Notice, Phase 2 - March 2017

Major funding source: Federal and State

Phase: Phase 2 Coming Soon

UPC: Phase 1: 90725; Phase 2: 109272

State ID: Phase 1: 0771-053-P42, P101, R201, C501; Phase 2: 0621-053-158, R201, C501

Federal ID: Phase 2: STP-5A01 (836), STP-5A01 (935)

Long/Lat: 39.030265, -77.582008

Locality: Loudoun

1 / 1
Phase 1 Construction - October 2016
2 / 2
Phase 1 Construction - October 2016
3 / 3
Phase 1 Construction - October 2016
4 / 4
Closed gravel portion of The Woods Road

Page last modified: June 15, 2019