Recently Completed: The Woods Road Improvements, Phase 2 in Loudoun County

Cost and schedule ►

Public outreach ►

The second phase of this project added turn lanes at the intersection of The Woods Road and Evergreen Mills Road. 

The first phase included realigning the road from just east of Understory Way to Evergreen Mills Road and reconstructing and paving the gravel portion. The new road features two ten-foot-wide travel lanes, as well as five-foot-wide paved shoulders for cyclists. 

More than 9,000 vehicles travel through the intersection of Evergreen Mills Road and The Woods Road each day.

Estimated Costs - Phase 1
Preliminary Engineering - $1.5 million
Right of Way Acquisition and Utility Relocation - $132,000
Construction - $3.9 million
Total: $5.5 million

Phase 1 was financed with state and Loudoun County funding.

Estimated Costs - Phase 2
Right of Way Acquisition and Utility Relocation - $597,000
Construction - $1.9 million
Total - $2.5 million

Phase 2 is financed with federal and state funding.

Benefits 

The project aimed to improve safety and operations, as well as accommodate future expansion of the Loudoun County Landfill.

Major Milestones 

Location and Design Public Hearing - October 2013
Phase 1 Construction Start - 
April 2016
Phase 1 Open to Traffic/Substantially Completed - November 2016
Phase 1 Final Completion - April 2017
Phase 2 Begin Right of Way Acquisition/Utility Relocation - July 2017
Phase 2 Advertise for Construction - March 2019
Phase 2 Award Construction Contract - May 2019
Phase 2 Begin Construction - July 2019
Turn Lanes Open to Traffic - March 2020
Phase 2 Final Completion - June 2020

Resources

Contact Info:

Mehrdad Naderi, P.E.
Construction
(Phase 2)

Michael Gleasman, P.E.
(Phase 1)

Project Photos

Other relevant links:

"De minimis" Public Notice, Phase 2 - March 2017

Previous Meetings >>

Major funding source: Federal and State

Phase: Phase 2 Recently Completed

UPC: Phase 1: 90725; Phase 2: 109272

State ID: Phase 1: 0771-053-P42, P101, R201, C501; Phase 2: 0621-053-158, R201, C501

Federal ID: Phase 2: STP-5A01 (836), STP-5A01 (935)

Lat/Long: 39.030265, -77.582008

Locality: Loudoun

x2close
1 / 1
list of photos
Pre-construction view of Evergreen Mills Road and The Woods Road intersection looking north
2 / 2
list of photos
Phase 1 Construction - October 2016
3 / 3
list of photos
Phase 1 Construction - October 2016
4 / 4
list of photos
Phase 1 Construction - October 2016
5 / 5
list of photos
Closed gravel portion of The Woods Road

Page last modified: June 2, 2020