Map of construction project districts

Recently Completed

Walney Road and Willard Road

Signal upgrade in Fairfax County

Project at a Glance

Begin Date
Fall 2013

Est Completion Date
April 24, 2014

Cost
$404,000

Contractor
Phillip Clarke Electric

Locality
Fairfax

District
Northern Virginia

Contact
Sid A. Siddiqui, P.E.
Senior Engineering Supervisor, NRO Traffic Engineering
703-259-1051

About the Project

This project upgraded the existing traffic signal at Walney Road and Willard Road in Chantilly. Phillip Clarke Electric completed the work on April 24th, 2014.

Estimated Project Costs
Preliminary engineering:  $50,000
Right of way:   $98,000
Construction:  $256,000
Total:  $404,000

View a plan sheet for the project.
 

State Project: 0657-029-920,P101,M501  UPC: 98281