I-95 Bridge Rehabilitations |
| Improvements to 11 bridges along I-95 in Richmond starting in 2010 |
Project at a Glance
Begin Date
April/May 2010
Est Completion Date
Completion in 4 to 4.5 years from construction start
Cost
$120 million (estimate)
Lengths and Limits
7 miles
Locality
Henrico
District
Richmond
April/May 2010
Est Completion Date
Completion in 4 to 4.5 years from construction start
Cost
$120 million (estimate)
Lengths and Limits
7 miles
Locality
Henrico
District
Richmond
Contact
Steve McNeely, project manager
804-524-6152
Project Details
This maintenance project involves the rehabilitation of 11 bridges along the Interstate 95 corridor in the city of Richmond and Henrico County between Lombardy Street and Upham Brook (just north of the I-64/I-195 interchange). The bridges will be rehabilitated in six phases.
The following bridges will be rehabilitated:
- Lombardy Street/CSX railroad
- Overbrook Road
- Sherwood Avenue
- Robin Hood Road
- Hermitage Road
- I-95 over the Boulevard
- Ramp A over the Boulevard
- Westwood Avenue
- Laburnum Avenue
- Upham Brook northbound (Henrico)
- Upham Brook southbound
- (Henrico)
I-95 Bridge Rehabilitation Project in Dashboard
Traffic Impacts
Construction activities will take place primarily overnight and may involve multiple lane and ramp closures, particularly when pre-fabricated sections of the bridge are transported along I-95 and installed.- I-95 lane closures will be weeknights between 8 p.m. and 6 a.m.
- VDOT will maintain one travel lane on I-95 in each direction and an emergency lane during lane closures.
- Expect detours on Richmond city streets overnight during bridge work.
- Possible weekend lane closures on I-95 from 8 p.m. Friday through 6 a.m. Monday. This will be communicated to drivers several days prior to the lane closures.
Contacts
Steve McNeely, project manager, 804-524-6152Public Affairs, 804-524-6179