Map of construction project districts

Under Construction

I-64 Pavement Rehabilitation

Improvements between I-95 interchange and Parham Road

Project at a Glance

Begin Date
Oct. 2009

Est Completion Date
Nov. 2010

Cost
$40 million

Lengths and Limits
I-64 east & west between the I-95 interchange and Parham Rd. (Exit 181)--approx. 5.6 miles

Locality
Henrico

District
Richmond

Contact
Steve Fritton, project manager
804-524-6430

Project Details

This project will involve repair and resurfacing of more than five miles of pavement along I-64 east and west between the I-95/I-195 Bryan Park interchange and Parham Road (Exit 181) to include ramps and merge lanes. 

Concrete repairs will begin in fall 2009. Major asphalt overlay will begin in spring 2010 with completion expected by late 2010. 9/22/09 News Release

Subscribe to I-64 Repaving e-mail updates.

Unsubscribe to I-64 Repaving e-mail updates.

Six Year Improvement Program

Traffic Impacts

The traffic management plan for this project will be coordinated with nearby projects such as the I-95 bridge rehabilitation project. There will be detailed lane and ramp closure time constraints. Drivers can expect:

  • Nighttime lane closures during the week
  • Weekend lane closures during the day and night
  • Short term detours for ramp work

Traffic Alert through Dec. 18, 2009

 

Contacts

Steve Fritton, project manager, 804-524-6430
Public Affairs, 804-524-6179