Map of construction project districts

Recently Completed

I-95 Richmond Bridge Restorations

Replaced 11 bridges

Area Maps

Project Photos

Project at a Glance

Begin Date
September 2010

Est Completion Date
June 2014

Cost
$106 million

Lengths and Limits
Lombardy Street (just north of exit 76) in Richmond to Upham Brook (near exit 82) in Henrico County

Contractor
Archer Western Contractors

District
Richmond

Contact
Scott Fisher, project manager
804-213-9740

News Release

MAJOR TRAFFIC IMPACTS END ON I-95 BRIDGE RESTORATIONS PROJECT

Four months ahead of schedule, $16 million saved

COLONIAL HEIGHTS — The Virginia Department of Transportation (VDOT) has ended all major traffic impacts on the I-95 Bridge Restorations project and work is nearly complete, more than three months ahead of schedule. The four year project rehabilitated eleven major structures along the I-95 corridor in the City of Richmond and Henrico County. The projected costs are expected to be well under the $106 million budgeted with a savings of nearly $16 million.

Construction for the safety improvement project began in September 2010 with restoration work to the piers and abutments for each of the eleven bridges. During construction, VDOT was able to use advanced technology to replace the bridges quickly and with little impact to drivers. “By replacing each bridge superstructure with pre-cast sections, we were able reduce the amount of time it takes to construct a new bridge, with minimum impacts to traffic,” said Scott Fisher, project manager. Drivers will enjoy extended working lives of up to sixty years for each structure.

“The coordination efforts among the contractor, localities and VDOT have been paramount in keeping this project on schedule,” said District Administrator Tom Hawthorne. “We’re pleased to be able to end major traffic impacts so early.”

Over the past few months, crews have completed final paving, pavement markings and have replaced the last two bridges at Upham Brook in Henrico County. The contractor, Archer Western, will complete landscaping and other minor construction activities through October. This work will have little to no impact on traffic.

The project spanned approximately seven miles along Interstate 95. Approximately 150,000 vehicles travel through the corridor each day.

To find out more about the I-95 Bridge Restorations project, visit i95bridges.org.

Videos

VDOT/Richmond Flying Squirrels Baseball Public Service Announcement, Aug. 2013

Time lapse photography: I-95 northbound bridge replacement at Overbrook Road March 15-18, 2013 (9 bridge sections)

Time lapse photography: I-95 southbound bridge replacement at Overbrook Road March 1, 2013

U.S. Secretary of Transportation, Ray LaHood, visits the I-95 Bridge Restorations project - Jan. 25, 2012

Time lapse photography: Laburnum Ave. bridge replacement Oct. 23, 2011

Animation showing how bridge sections will be replaced

Project Overview

Talking with the project manager

Facebook Sharing

VDOT encourages the sharing of information about the I-95 Richmond Bridge Restorations project via individual Facebook pages. Please use this link to access image content that is ready to be published about the project. 

Use of these images is FREE; no copyright protections apply. Once you’re at the VDOT Facebook page, click your preferred image and then share it with your network on Facebook. The image will publish to your newsfeed wall with a brief description of the project and where to go for more information. The images will be updated regularly, so please check back often.

VDOT is replacing 11 bridges on I-95 in metro Richmond

This four year project covers a seven-mile stretch of I-95 between Lombardy Street in Richmond and Upham Brook in Henrico County. The following bridges have been replaced:

  1. Laburnum Ave. (Oct. 2011-April 2012)
  2. I-95 South Ramp to Boulevard (southbound May 2012, northbound Sept. 2012)
  3. Westwood Ave. (southbound June 2012, northbound Oct. 2012)
  4. Boulevard (southbound June 2012, northbound Aug. 2012)
  5. Hermitage Rd. (southbound July 2012, northbound Sept. 2012)
  6. Sherwood Ave. (southbound Nov. 2012, northbound April 2013)
  7. Robin Hood Rd. (southbound Nov. 2012, northbound April 2013)Interstate 95 bridge rehabilitation project map
  8. Overbrook Rd. (March 2013)
  9. Lombardy St. (May-Oct.2013)
  10. Upham Brook northbound (Nov. 2013- June 2014)
  11. Upham Brook southbound (Nov. 2013-June 2014)

 

 

How did the four year construction project impact traffic?

When beams and bridge decks were replaced, I-95 traffic was reduced to one travel lane in each direction. This was typically done Sunday through Thursday nights from 8 p.m. to 6 a.m. By working at night, we will impact fewer drivers and reduce motorist delays. 

The contractor was permitted to close one travel lane on I-95 in each direction for daytime bridge work Monday through Friday from 8:30 a.m. to 3 p.m. 

Lane closures were not permitted during morning or afternoon rush hour except for emergency repairs.

I-95 ramps and city streets under the bridges were closed periodically during bridge replacements. This only occurred intermittently, Sunday through Thursday nights from 7 p.m. to 6 a.m.

Background

The project began in 1999 with the successful replacement of the James River Bridge and Broad Street bridges.

Since then, VDOT accumulated funds and restored the remaining 11 bridges along this vital transportation corridor.

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: Aug. 19, 2014